Hongmyung Lim FDOT PM to coordinate
contract time with the following distribution email: 971130
Prior to beginning the Stage I Scope Development, a meeting will
be held with PD&E for a debriefing of the project. History of
the project including, previous meetings, project commitments,
key decision makers, controversial issues, etc. will be discussed.
At this stage, the CAP level and effort should be determined for
scope negotiations. A list of stakeholders should be acquired from PD&E.
Click outside this box to close 299010
The FDOT Project Manager will send an email to D5-Work Program
to open phase 31 for in-house timesheet charges.
Click outside this box to close 164010
This activity is for advertised projects only. The Stage I Scope
of Services is the Scope of Services (SOS) boilerplate. The SOS
will be used in conjunction with the Technical Scope or Preliminary
Engineering Report (PER) or other technical documents to prepare a
Stage II Scope of Services for advertisement. Comments provided by
Local Agency members should be considered in the project scope
development. See guidance document for specific instructions.
Click outside this box to close 230130
For Consultant Acquisition projects: This evaluation is a coordination
effort (email, meetings, field visits, etc.) for FDOT disciplines and
other stakeholders to review and develop scope items. The Stage II
Scope of Services should be completed prior to submitting the Consultant
Package to PSU.
For CSC and DW contracts: This evaluation can be
accomplished at the Finalize Scope/Prelim Units meeting and the
consultant PM will develop the Stage II Scope of Services.
Click outside this box to close 231010
Package submitted to Professional Services to begin the Consultant Procurement process.
This includes items such as the Stage II Scope, workgroups to be advertised, PM name, etc.
(Note: see Professional Services Request Form).
Click outside this box to close 230140
This coordination effort is to finalize the Scope of
Services that will be part of the signed contract. This
typically occurs after negotiating staff hours. If
necessary, the FDOT PM should organize the meeting and
invite the Consultant PM, EORs, DCPME and any other
disciplines needed to complete the Scope of Services.
Click outside this box to close 232010
Professional Services will post the advertisement and associated
documents online for projects which it is seeking to procure consultant
services for. Consulting firms will use the information contained in the
advertisement to prepare Letters of Response. These letters are used as
determining factors in the selection of firms who will be considered for
long-list and short-list selections. Once the advertisement is posted,
FDOT is not allowed to discuss or share information about the project
with anyone pursuing the project.
Click outside this box to close 402010
This is a meeting that is conducted by Professional Services and includes
the District Secretary, Directors, Technical Review Committee (TRC) Members
and the FDOT Project Manager. The TRC rankings of the short-listed firms
will be presented to the Secretary and Directors who will then have the
opportunity to ask questions or provide additional feedback before a
selection is made. At the conclusion of the meeting, a firm will be
selected for the contract to be awarded.
Click outside this box to close 900020
The purpose of this meeting is to finalize the units (develop quantities
for each task) prior to staff hours negotiations. The consultant should
give a brief overview of the project, including the limits and description,
and any proposed scope changes. Any constraints should be identified
including PD&E commitments, contamination, existing and proposed
development, constructability, and local coordination. The consultant is
responsible for submitting the final units document before the date
specified by FDOT. This meeting is organized by the Contract Negotiator.
Click outside this box to close 164030
During this timeframe, The FDOT Project Manager, FDOT Design Experts,
and Consultant/Sub consultants negotiate all design activities
necessary to successfully complete the project.
Click outside this box to close 233020
Professional Services (Contract Writer) requests the
final negotiated dollar amount via the Contract Funds
Management System (CFM). The FDOT Project Manager is
responsible to ensure this task is completed by the
Contract Writer. If the final negotiated design fee
is higher than the preliminary estimate in Work Program,
the FDOT Project Manager shall submit a Work Program
form to be able to encumber the necessary funds or
renegotiate staff hours.
Click outside this box to close 233010
All Work Program funding must be authorized for the
contract to be encumbered. This is also known as the
Lockdown date. The Professional Services Contract
Writer will request the final negotiated dollar amount
via the Contract Funds Management System (CFM) to
encumber the funds. The FDOT Project Manager is
responsible for ensuring adequate funding has been
programmed in the correct Work Program Financial
Project Number (FPN). Note: If the final negotiated
design fee is higher than the amount programmed in
Work Program, the FDOT Project Manager shall submit
a Work Program form for the full amount required.
Click outside this box to close 263020
LDCA stands for Location and Design Concept Acceptance. Once FHWA
has reviewed and concurs with the design concept, commitments and
project documentation, they will issue Location and Design Concept
Acceptance. This occurs after the public hearing and when the final
environmental and engineering document is complete.
Click outside this box to close 250010
For Consultant Acquisition Projects, this date, also labeled NTP
(Notice to Proceed), is the date that the Consultant firm is authorized
to proceed with work on the Contract. For Continuing Service Contracts
(CSC) and District Wide (DW) contracts, this date is when the Task Work
Order is executed by Professional Services and work can proceed on the
Contract as directed by the FDOT Project Manager. The FDOT Project Manager
should receive a copy of Notice to Proceed or the executed TWO from the
Contract Writer or Contract Manager.
Click outside this box to close 113005
This activity is for our EOR/Consultant to investigate the value of additional safety improvements and
speed management strategies for inclusion into our project scope. Using the designated Target speed for
the project, the improvements should support the Departments Vital Few Safety initiative and Target Zero
goal. The EOR/consultant will analyze their project for any safety enhancing improvements and forward the
evaluation to the FDOT PM for consideration into the project scope. When the documentation is received,
the FDOT PM and EOR/Consultant PM will work informally with FDOT internal disciplines including but not
limited to Roadway, traffic ops, PLEMO and the Office of Safety staff. Once resolved and comments are
addressed, the Design Analysis Evaluation will be placed on Collaboration Meeting agenda for final review
and approval. To facilitate approval, the documentation should include additional construction costs
associated with the proposed countermeasures and the countermeasures should be prioritized based on crash
analysis (may be divided into long- and short-term recommendations). Depending on the newly approved
proposed scope additions, the FDOT PM will initiate a design SA as needed and will continue working toward
the next phase of design.
Click outside this box to close 367010
The purpose of this activity is to identify all Design Variations
and Exceptions. When the Department's criteria are not met, a Design
Exception or Design Variation is required. Design Exceptions are
required when proposed design elements are below both the Department's
governing criteria and AASHTO's new construction criteria for the
Controlling Design Elements. Design Variations are required when
proposed design elements are below the Department's criteria and
where a Design Exception is not required. All Exceptions and Variations
shall be processed in compliance with the FDM. It is the responsibility
of the EOR to identify all variations and exceptions including Utility
Design Alternatives. Utility Design Alternatives will be identified
anytime compliance with the UAM is not reasonably achievable. It is the
responsibility of the utility owner to initiate a request for a design
alternative approval. All Utility Design Alternatives shall be processed
in compliance with the UAM.
Click outside this box to close 900030
Soon after Project Execution/PE Begin, the FDOT Project Manager
(PM) should meet with the Consultant PM and outline the department
expectations. A QC Plan, Risk Assessment Project schedule and Public
Engagement Plan strategy will be discussed during this meeting. The
Consultant should immediately begin updating the LRE to reflect the
negotiated scope and should complete this task within the first twenty
days of the project. The Consultant and FDOT PM should coordinate the
preliminary proposed R/W acquisitions with R/W Administration to
generate a preliminary R/W estimate (if needed). The Consultant should
also provide any Computer Security Access Requests to the FDOT PM.
See link for agenda template and documents. The agenda and documents
can be modified to fit the Project scope and expectations.
Click outside this box to close 290010
The Community Awareness Plan consists of a Public Engagement Plan
(PEP) Strategy presentation. The PEP presentation is a brief
PowerPoint presentation, identifying project challenges associated
with public acceptance. The PEP should include specific strategies
and techniques the team will use to gain public acceptance. This
strategy will identify proposed milestone dates and methods of
informing people to include, but not limited to, Public Meetings/
Workshops etc. Specific Public/Agency issues may include: access
management, removal of street parking, landscaping, alternative
intersections, aesthetic treatments, etc.
Click outside this box to close 359040
The Prime Consultanting Firm Project Manager shall
contact the appropriate City Manager and County Manager
offices, informed of the beginning of the design phase,
and inquire as to which City/County Departments need to
be included on the project correspondences. Contact the
appropriate liaison from Government Operations Unit for
assistance in obtaining local contact list. Click outside this box to close 325020
The Board of Trustees of the Internal Improvement Trust Fund of
the State of Florida (TIITF) Determination: This applies to any
water body that lies within the project limits (both existing and
proposed right of way) to determine if it is sovereign submerged
lands. If the determination is no, then no further action is
required. If the determination is yes, and we have an existing
easement with TIITF (DEP) and no new areas are affected, then no
further action is required. If the determination is yes, and we do
not have an easement over the existing right of way and/or new
areas are affected by an acquisition, the PM should coordinate with
Surveying, R/W and Permitting to obtain the TIITF easement. A DEP
determination of “proprietary authorization need not apply” may
still require regulatory approvals.
Click outside this box to close 900010
During this time frame, the FDOT Project Manager will provide the
schedule template to the Consultant PM. The Consultant PM will
develop a project-specific schedule (baseline schedule) which
achieves the milestone dates required by the Department and agreed
upon by both parties. This scheduling process should be completed
within twenty days after Project Execution/PE Begin. Once
complete, the baseline schedule should be forwarded to the
Production Management Office. This schedule shall be used to
measure the Consultant’s performance throughout the project.
Click outside this box to close 233030
After the Consultant prepares an estimated design fee for the Plans Update,
the FDOT Project Manager shall submit a Work Program form to encumber the
additional funds necessary.
Click outside this box to close 170050
Project Network Control (PNC) determines or establishes horizontal
and vertical control points for project use. Horizontal positions
are based on the Florida State Plane Coordinate System and must use
North American Datum of 1983 (NAD83), 1990 or later adjustment.
Vertical control (benchmarks) elevations are based on North
American Vertical Datum (NAVD) of 1988.
Click outside this box to close 294010
The Typical Section Package is prepared by the EOR to establish and
document project controls, cross sectional elements Design Variation/
Exceptions, typical transverse geometry, as well as address safety
related issues for the project. The Typical Section Package should
be prepared in accordance with FDM 120 and submitted to the FDOT PM.
The FDOT PM should start the Typical Section approval process prior
to Phase II plans.
Click outside this box to close 106210
Establish or retrace the original survey alignment for which all
proposed improvements, right of way, and topography for the project
are referenced. Key point monumentation and monumentation reference
points are set after alignment acceptance by FDOT staff.
Click outside this box to close 170010
Survey necessary to establish the controlling boundary lines and/or
individual property lines for all properties affected by potential
acquisition takings. This includes section and subdivision retracements
along with miscellaneous property corner ties. The establishment of all
existing right of way lines (which are property lines) falls in this survey.
Click outside this box to close 106010
Survey necessary for designers and engineers of record to
utilize to set geometry to cut cross-sections. There are
different types that include Topography (picking up all
2-D horizontal features), DTM (Digital Terrain Model which
is a 3-D graphical representation of the existing ground),
cross-sections (which can be surveyed at critical isolated
locations), utility designates and Verified Vertical Elevation
and Horizontal Location (VVH), etc.
Click outside this box to close 424020
At this meeting, scheduled by Right of Way, the Design Team selected for the project
will meet with the Right of Way Cost Estimate/Design Support Team assigned to the project for the following purposes:
1) Reviewing the PD&E Right of Way Cost Estimate for potential changes to be incorporated in the scheduled R/W Estimate-Scope (Activity 298010).
2) Reviewing the Right of Way Cost Estimate parcel numbering protocol to be incorporated in all scheduled Right of Way Cost Estimate project
milestone updates (Activity Codes 298010 through 298090) and Special Right of Way Cost Estimates developed to support
design decisions. 3) Reviewing the proper format, transmission and dissemination of project data, exhibits and information
relative to the Right of Way Cost Estimate/Design Support functions. In preparation for this meeting, the EOR should be
familiar with FDOT Design Manual Chapter 113 Right of Way Requirements. This meeting should be scheduled by and coordinated with the Deputy Right of Way
Manager – Valuation Services, or Right of Way Cost Estimates Coordinator.
900070
The Stakeholders Meeting is the project kickoff meeting for
the internal and external stakeholders. At this meeting, the
consultant or in-house EOR discusses the scope of the project
with the Local Agencies, utility companies, transit agencies,
and key external stakeholders. The purpose of this meeting is
to solicit all information from these stakeholders that may
affect the scope of the project. The stakeholders should submit
their requests to the FDOT Project Manager no later than two
weeks after the meeting. If the scope changes as a result of
the Stakeholders meeting, then the EOR should update the LRE
immediately so as to reflect the most up-to-date construction
cost for the project (the same holds true if R/W requirements
change due to this meeting, the R/W Estimate needs to be updated).
To facilitate effective involvement by external stakeholders and
FDOT field units, it is preferred to conduct these meetings at a
local agency facility (if possible). A field review immediately
prior to the meeting may be beneficial, however not required, to
familiarize the team with the project. The Consultant Project
Manager shall set up the meeting, prepare the agenda, and develop
the meeting minutes.
Click outside this box to close 256010
The FDOT Project Manager contacts PLEMO Systems Planning by
selecting the link titled “Traffic Request Portal” to request
traffic volumes for ESAL analysis for the length of the
roadway under design. The Traffic Request Portal will have
the information for the project automatically populated.
Planning will complete report in-house, or utilize their
Districtwide Traffic Consultant to prepare a traffic ESAL
(equivalent single axle load) report consisting of information
needed to prepare a pavement design. Note: This activity is
contained in the default Primavera schedule template generated
for every project; not every project will require an ESAL
analysis depending on work type. Please consult Planning or
Roadway Design for questions regarding this. Also, for technical
issues regarding the Traffic Request Portal, please contact Planning.
Click outside this box to close 933020
The purpose of the event is to define all potential Local
Agreements and documentation required to meet the Production
deadline. The activity will be a single event with at least
a 10-day duration prior to Design Team Meeting (Major Projects)
and Initial Plans Review (Minor Projects). When Local Funds
(LF) are required Work Program will be notified by completing
a Work Program form for the local funds as a placeholder. The
estimate will be developed by the consultant with the help of
the PM and the estimates office. Once a potential agreement
is identified it will be taken to the Agreements Intake Meeting
(AIM) for consultation. The PM will then proceed to incorporate
the Agreement activity deadlines into schedule in a logical
sequence of event to address the type of agreement. Some example
Activities include Draft Agreement Complete, Final Agreement
Complete, Council Meeting Approval, Funds Received from Local
Agency, etc. The ownership of the Activity will clearly be
identified and placed in the Production Notes.
Click outside this box to close 298010
This is the first of four scheduled Right of Way cost estimate updates.
The FDOT Consultant Project Manager and the EOR will need to provide the FDOT R/W Cost Estimates/Design
Support team an update of the anticipated right of way needed for the project. The Consultant Project Manager
will need to include all real property parcel impacts including potential ponds, corner clips, and strip takes.
The impacts will need to be visualized on an appropriate exhibit and quantified on the Excel spreadsheet format
provided at the Right of Way Kickoff Meeting or suitable alternative worksheet approved by the Right of Way Cost Estimate
Coordinator. A special estimate will need to be done for alternate ponds identified in the negotiated scope.
Click outside this box to close 264000
The Utility Coordinator shall send the Advance Utility Notification
letter to all utilities within the project limits, with the
pertinent project information. The DUO should program funds for any potential reimbursement
and/or UWHC estimates and this time.
Click outside this box to close 304010
The Pavement Section in the Materials and Research Office
will provide necessary coring for the roadway and will
provide the report with milling and resurfacing recommendations
to the FDOT Project Manager. The EOR and FDOT PM initiate
coordination and should work closely with the Materials office
to set the areas to be cored and analyzed early in the process.
Click outside this box to close 271010
The Pond Siting Report (PSR) documents the evaluation of
alternative stormwater management facilities for each roadway
drainage basin along the project corridor. The primary types
of stormwater management facilities evaluated are retention/
detention ponds, and their locations and sizes are based on a
number of hydrologic, hydraulic, environmental, and right of
way considerations that are summarized into a selection matrix
that is used to designate the preferred alternative for each
basin. Findings from the Environmental Look Arounds (ELA) shall
be documented in the reports for future follow up as the design
moves forward. The FDOT Drainage Manual (Chapter 5) and The FDOT
Drainage Design Guide (Chapter 9) provides a good overview of
pond site selection considerations.
Click outside this box to close 146005
Title Search Work is performed by FDOT Surveying & Mapping
Title Unit and/or their consultant. The R/W Surveyor is required
to submit a property appraisers map with all properties marked
that are affected by the project (this will not include those
properties that are affected by minor driveway connections only).
At this stage of design development at least 85-95% (if not all)
of the affected parcels are known. Also, after the initial
identification of properties affected, the EOR must keep the
Surveyor updated if new properties are identified and the Surveyor
must submit follow up title search requests.
Click outside this box to close 170250
PNC (Project Network Control) Database is the compilation of the
final horizontal and vertical control coordinates along with all
the final support documentation (station reports, benchmark forms,
photographs, etc.).
Click outside this box to close 294020
When the development of the draft Typical Section is complete
the Consultant EOR will submit it to the FDOT PM for review and
submittal. Once the draft Typical Section is received the FDOT PM
will coordinate with the Roadway Design Department and conduct an
initial review. Upon review acceptance the FDOT PM will upload the
Typical Section into Project Suite (PSEE) for Design Document Approval.
Click outside this box to close 925010
This is the first of three letters sent to property owners
whose property has been selected as a preferred pond site
location for a project. The intent of the letter is to allow
the property owner input early in the design process. An
example letter can be found on the FDOT Drainage Design
website. The letter should include a sketch showing parcel
boundaries, location and approximate size of the pond(s).
This letter should be sent by certified mail to the property
owner by the Prime Consulting Firm on current FDOT Letterhead
in the approved format for FDOT Correspondence.
Click outside this box to close 587010
VVH stands for Verification of Vertical and Horizontal. During
this time, the EOR shall ensure the majority of VVH’s have been completed
prior to Initial Plans Review. This would include, but not
limited to, proposed signals, bridge foundations and drainage
structures. Plans to be updated with test holes and callouts, as well as
the Summary of Verified Utilities Sheet(s). It is noted additional VVH’s may
be necessary if additional modifications are made to the plans or additional
information is needed.
Click outside this box to close 109110
This meeting, between the Design Engineer's drainage staff and
the FDOT District Drainage Engineer or Assistant District Drainage
Engineer and District Permit Coordinator, is an informational
meeting where both parties discuss the project's stormwater
management concepts, drainage issues, permitting issues, district
specific criteria, right of way requirements, level of effort, new
or future storm water design or rule changes, etc. Decisions on
certain design and permitting parameters will be made depending on
the level of detail known at the time of this meeting. This activity
can be combined with the Permit Coordination Meeting.
Click outside this box to close 260010
In order to have this activity completed, all applicable
signatures on the Typical Section cover sheet must be
obtained including concurrence from the District Design
Engineer, District Traffic Operations Engineer, ISD
Manager and FHWA (if applicable). Click outside this box to close 106310
When sufficient survey has been performed to determine
the original survey alignment and a drawing has been
prepared, a meeting is scheduled between the Consultant
Surveyor and the D5 District Surveyor and/or his/her
designee. The Consultant Surveyor presents their analysis
of the field data recovered and determination as to the
location of the original survey alignment. This is a critical
procedure since the original survey alignment is usually the
basis for establishing the existing right of way. Key point
monumentation and monumentation reference points are set
after alignment acceptance by FDOT staff.
Click outside this box to close 170150
The R/W Control Survey Map is a certified survey drawing
showing the graphical representation of the survey data
(Monumentation recovered or set) and the survey decisions
made by the Consultant Surveyor regarding the location of
controlling land lines and property lines. The 30% R/W
Control Survey Map stage depicts the accepted survey alignment,
all section retracements, and reference points recovered or
set at key points along the survey alignment. Subdivisions
are shown graphically on the key map(s) at this stage.
Click outside this box to close 257010
This is the date that the final draft of the Design Traffic
Report is received by the FDOT Project Manager. A copy of
this report should be sent to the Prime Consulting Firm
Project Manager/EOR and a copy should be filed in the project
files. It is important to remember that this design traffic
report should be updated approximately every two years to
account for current trends.
Click outside this box to close 145040
The purpose of this meeting is to discuss all permitting tasks
and to determine which environmental permits are required (i.e.
water management districts, Army Corps of Engineers (ACOE), Coast
Guard, Florida Department of Environmental Protection (FDEP)).
Attendees should include the Consultant Drainage Engineer, Consultant
Biologist, FDOT Reviewing Drainage Engineer, FDOT Permit Coordinator,
Consultant Project Manager and FDOT Project Manager. Items of
discussion will include: corridor wetland delineations, pond site
wetland estimates, meetings held with regulatory agencies, field
review with regulatory agencies, potential impacts to protected species
habitat, review of pond site alternatives impacts to wetlands/protected
species habitat, and confirmation all commitments from PD&E documents.
Agenda is attached as a link.
Click outside this box to close 271110
This is the Department's review of the Consultant's Draft
Pond Siting Report. The FDOT Project Manager should upload
the report to ERC and assign relevant staff to the review,
including Drainage, Geotechnical, and Right of Way.
Click outside this box to close 272030
Designer and engineer of record shall update permit(s)
for plans update phase. These permits include but are
not limited to water management district permits, ACOE,
Coast Guard, FFWCC, etc.
Click outside this box to close 313010
The completion of this task is culminated by the arrival
of the final Pavement Survey and Evaluation Report (aka.
PS&E or PSE). This report contains an analysis of the
existing roadway including, but not limited to crack depth,
composition, typical, milling recommendations, and possibly
a DYNAFLECT test (which is used to determine the resilient
modulus). This report is instrumental in development of the
pavement design for the roadway rehabilitation. A copy should
be provided to the design EOR or Consultant Project Manager.
Click outside this box to close 925020
This is the second of three letters sent to property owners
whose property has been selected as a preferred pond site
location for a project. The intent of the letter is to allow
the property owner input early in the design process. An example
letter can be found on the FDOT Drainage Design website. The
letter should include a sketch showing parcel boundaries, location
and approximate size of the pond(s). This letter should be sent
by certified mail to the property owner by the Prime Consulting
Firm on current FDOT Letterhead in the approved format for FDOT
Correspondence. Note: The second letter is not necessary if the
first letter established coordination with the property owner.
Click outside this box to close 271020
The Final Pond Siting Report (PSR) documents the evaluation
of alternative stormwater management facilities for each
roadway drainage basin along the project corridor. The primary
types of stormwater management facilities evaluated are
retention/detention ponds. Their locations and sizes are
based on a number of hydrologic, hydraulic and environmental
parameters. These parameters are summarized into a selection
matrix that is used to designate the preferred alternative for
each basin. Findings from the Environmental Look Arounds (ELA)
shall be documented in the reports for future follow up as the
design moves forward. The FDOT Drainage Manual (Chapter 5) and
The FDOT Drainage Design Guide (Chapter 9) provide a good overview
of pond site selection considerations. Comments from the Department's
review of the Draft Pond Siting Report should be incorporated in
the Final Pond Siting Report.
Click outside this box to close 315020
The 30% R/W Control Survey Map consists of; 1) Cover Sheet
that includes general notes, legend, survey certification
and, 2) Key Map Sheet(s) usually prepared at a scale of 1”
= 400’ which show the complete alignment, section data with
appropriate ties to the survey alignment, along with recorded
subdivisions depicted graphically.
Click outside this box to close 315120
The 60% R/W Control Survey Map builds upon the 30% R/W
Control Survey Map. This stage includes; 1) Detail Sheets,
usually prepared at a scale of 1" = 40' which show complete
field ties and geometry for existing right of way, side
street right of way, sections, subdivisions and any other
controlling property lines as scoped, along with the appropriate
ties to the survey alignment and, 2) Reference Point Detail
Sheet(s) usually prepared at a scale of 1" = 40' which depict
the survey alignment control points and associated reference
points. Basically, this is a complete map at this stage.
Click outside this box to close 106110
The majority of the design survey activities have been completed
to support the Line & Grade and Initial Plans development phases.
There will be some outstanding items such as final pond site
surveys and utility surveys at potential conflict locations.
The design survey TOPO, drainage, utility and DTM MicroStation
drawings have been provided to the EOR. The EOR is responsible
for accepting the design survey as to whether it meets his/her
needs to support the design development.
Click outside this box to close 925030
The last of three letters sent to property owners whose
property has been selected as a preferred pond site location
for a project. The intent of the letter is to allow the
property owner input early in the design process. An example
letter can be found on the FDOT Drainage Design website. The
letter should include a sketch showing parcel boundaries,
location and approximate size of the pond(s). This letter
should be sent by certified mail to the property owner by the
Prime Consulting Firm on current FDOT Letterhead in the approved
format for FDOT Correspondence. Note: Do Not send this letter
if previous correspondence established coordination with the
property owner.
Click outside this box to close 113010
During the Line & Grade phase, the Designer/EOR is
developing the preliminary design for the project. This
includes preliminary design geometry (including, but not
limited to horizontal alignment, setting preliminary grades,
evaluating driveway connections, setting back of sidewalk profiles,
designing preliminary side street geometry/profiles, obtaining
and setting water elevations affecting grades, evaluating bridge
clearances, etc.). Also, being developed during this time frame
are the typical sections, pond siting report, the pavement design,
exceptions and variations. If roundabout development is part of
the project and an Alternative Intersection Review Package is
required per FDM Chapter 116, the Designer shall use the “Design
and Control Vehicle Form” that is included in the links for this
activity.
Click outside this box to close 265010
The CONSULTANT shall schedule (time and place), notify participants, and conduct a preliminary utility meeting with all
UAO(s) having facilities located within the project limits for the purpose of presenting the project,
review the current design schedule, evaluate the utility information collected, provide follow-up information on
compensable property rights from the FDOT Legal Office, discuss the utility work by highway contractor option with
each utility, and discuss any future design issues that may impact utilities. This is also an opportunity for the UAO(s) to
present proposed facilities. The CONSULTANT shall keep accurate minutes and distribute a copy to all attendees. Meeting can be
in person or virtual, as determined by the DUO. Click outside this box to close 114010
The Bridge Hydraulics Report (BHR) is a supporting document for the BDR and
consists of specific hydrologic, hydraulic, stream stability, and
potential scour information related to a bridge over a waterway. This report
should identify the minimum hydraulic bridge openings, as well as, the minimum
clearance above the design high water level. The BHR is included with the BDR
review\submittal in ERC. The FDOT Drainage Manual (Chapter 8) and the FDOT Drainage
Design Guide (Chapter 5) list the minimum information that must be included in the
Bridge Hydraulics Report (BHR). The Bridge Hydraulics Recommendations Sheet (BHRS)
provides a single reference that summarizes the findings and recommendations of the
hydraulic analyses. Details in the FDOT Design Manual (Chapter 906) provide a guide to
populate the BHRS. Location Hydraulics Report to be prepared in conjunction
with the bridge analysis during the PD& E phase (Phase I).
Click outside this box to close 271120
This is the Department's review of the Consultant's Final
Pond Siting Report. The FDOT Project Manager should upload
the report to ERC and assign relevant staff to the review,
including Drainage, Geotech and Right of Way.
Click outside this box to close 133010
The Pre-BDR meeting shall include the FDOT Geotech Office, the FDOT
Structures Office, FDOT Structures Maintenance, the Structures EOR,
the Geotech EOR, FDOT Drainage. FDOT Environmental Permitting, Drainage
EOR, Environmental Lead, the FDOT Project Manager, and the Prime Project
Manager. The intent of the meeting is to discuss the preferred foundation type,
available loads and preliminary pile tip elevations. A follow-up meeting prior
to the Geotech Foundations Report for BDR/BHR submittal may be necessary. Click outside this box to close 221010
Access management is the systematic control of location,
spacing, design and operation of driveways, median openings,
interchanges and connections to a roadway. Proper access
management can improve the overall safety and efficiency of
a roadway by reducing conflict points along a corridor. For
widening projects, the PD&E report generally provides a proposed
median access plan. During design, the EOR should review and
re-evaluate the proposed access classification and access
management strategy. The access management report should be
signed and sealed by a traffic engineer, prepared in accordance
with FAC 14-97, FDOT's Median Handbook and related guidance to
address: existing median access (if applicable); existing and
future development/traffic demand; and recommended median access
plan. Preferred output includes aerials with proposed access plan
shown, along with table of access plan showing spacing, type and
location of proposed median openings and/or closures, along with
sufficient narrative to explain basis for access management
decisions. Note: Changes to property access will require a Public
Hearing.
Click outside this box to close 133020
This report shall present foundation alternatives analysis and
the preferred foundation selected at the Pre-BDR meeting.
Click outside this box to close 367020
On this date, all design Exceptions/Variations shall be
approved and obtained in order to proceed to the plans
submittal. All Utility Design Alternatives shall be submitted
prior to plans submittal. This package shall be submitted
to PSEE by the FDOT project manager, when appropriate.
Click outside this box to close 197010
The EOR prepares a pavement design package based on
guidelines outlined in the Flexible Pavement Design
Manual and the Rigid Pavement Design Manual. The
Pavement Design will be submitted to the FDOT PM to
start the Pavement Design approval process. Click outside this box to close 197015
The EOR incorporates review comments received from the FDOT D5 Pavement Design Engineer into the Pavement Design Package.
Once complete, the Pavement Design will be resubmitted to the FDOT PM for final approval by the FDOT D5 Pavement Design Engineer. Click outside this box to close 115010
The Bridge Development Report (BDR) is intended to establish the basic parameters
for the bridge design that will affect the work done in the design and plans
preparation phase. The BDR phase will contain sufficient detail for the justification
of the proposed bridge type. The level of effort is dependent upon the complexity of
the project. The BDR/30% Structures Plans should be included with the Roadway Phase II
submittal in ERC. Reviewers include Structures Design, Central Office Structures Design
(Category II Structures), Drainage Design, Structures Maintenance, Geotech, Construction and FHWA (if needed). Click outside this box to close 900060
The objective of this meeting is for the FDOT Project
Manager and EOR to meet informally with the City/County
Staff, review the major design details affecting the
local agencies, and discuss the progress on resolving
the local agency's concerns. The meeting should be held
at either the City or County offices and prior to
finalizing Initial Plans (Phase II).
Click outside this box to close 271030
This is the final deliverable of the reviewed and
approved draft PSR. Copies of this report shall
be retained be the FDOT PM and the District Design
Drainage Engineer.
Click outside this box to close 301010
Line & Grade meetings are intended to be utilized for
projects requiring reconstruction, new construction,
widening with grade changes, or a combination. The
meeting is intended to review and discuss the preliminary
design geometry and challenges including, but not limited
to horizontal alignment, grades, driveway connections,
back of sidewalk profiles, side street geometry/profiles,
water elevations affecting grades, bridge approach grades,
bridge clearances, etc. The EOR should provide information
on the project including decisions made and direction the
design is going. An agenda will be used to assure all major
project elements are discussed. After the meeting, both
the construction estimate and the R/W estimate should be
updated to account for any new directions given during
this meeting.
Click outside this box to close 339010
Value Engineering is the systematic application of function-
oriented techniques by a multi-disciplined team to analyze and
improve the value of a product, facility, system, or service.
A Value Engineering Study is usually performed for major
projects. This can be done during PD&E or shortly after
the Design phase begins. The FDOT Project Manager should work
with the District VE Manager to determine proper timing of the
VE Study (usually a 1-week process). After the dates are set
the FDOT PM will work with the VE manager and the EOR to prepare
all needed material to present to the VE Team. The FDOT PM and
the EOR should make themselves available during that week to
answer any questions from the VE Team, and they should be
present at the VE presentation usually held on the final day
of the Study. After resolution of the VE Recommendations, both
the construction and R/W estimates should be updated.
Click outside this box to close 372010
This is the pavement type selection report submittal activity
that is required for all applicable projects. This submittal
should be made to the District Pavement Design Engineer who
will QA the document, get District Design Engineer approval
and then transmit it to the State Pavement Design Engineer
in Central Office for further processing and submittal to
Industry for review and comment. Please refer to the
Department's Pavement Type Selection Manual for additional
information and description of applicable projects. This
activity is used for full roadway reconstruction or realignment.
Click outside this box to close 298030
This is the second of four scheduled Right of Way cost estimate updates.
The FDOT Consultant Project Manager and the EOR will need to provide the FDOT R/W Cost Estimates/Design
Support team an update of the anticipated right of way needed for the project. This will include all real property parcel impacts including
potential ponds, corner clips, and strip takes. The impacts will need to be visualized on an appropriate exhibit and quantified on
the Excel spreadsheet format provided at the Right of Way Kickoff Meeting or suitable alternative worksheet approved
by the Right of Way Cost Estimate Coordinator.
Click outside this box to close 238010
This line item is placed in the schedule as a reminder to
the FDOT Project Manager to perform an interim grade in the
FDOT Consultant Evaluation System. This is utilized so
that the Consultant Firm has some feedback as to their
current performance on the project. Any questions concerning
the Evaluation System can be addressed by D5 Consultant
Project Management – CES Administrator.
Click outside this box to close 131010
This report shall be submitted in ERC with the 60% plans and present the boring
profiles with groundwater information, final LBR recommendation, Roadway Soil
Survey sheet for inclusion in the contract plans, soil parameters and other appropriate
analyses. This report shall be updated for subsequent plans submittals based on plan
changes and review comments. Please refer to the Soils and Foundations Handbook
and the FDM Part 3, Chapter 318. Click outside this box to close 109010
Drainage design runs concurrently with Initial Roadway Plans.
This activity tracks the design of the drainage work involved
with the project. The BHR is tracked separately. Drainage design
can include items such as but not limited to pavement drainage,
storm drain design, open channel flow, culverts, stormwater
ponds, and optional pipe materials analysis (not due until 90%
Plans). An engineering evaluation should be conducted on all
relevant drainage elements of the project, both permanent and
temporary. A set of Review Checklists can be found on the State
FDOT website for Drainage Design, which provides guidelines for
common drainage and stormwater aspects of FDOT projects. The
designer will provide a Drainage Design Report to accompany all
phase submittals (signed and sealed for the Final Phase submittal)
that addresses the entire project design.
Click outside this box to close 113020
This is the preliminary development of Roadway Plans as
defined by FDM, Section 110. Upon completion of this phase,
utility coordination can begin, the permit application can
be submitted, and R/W requirements must be identified. The
LRE should be updated at the completion of this phase to
provide a more accurate construction cost. All pay items
should be loaded into AASHTOWARE Project (previously known
as TRNS*PORT)..
Click outside this box to close 315030
The 60% R/W Control Survey Map stage builds upon the
30% R/W Control Survey Map to depict the remainder of
the right of way survey elements such as; existing right
of way lines, subdivisions, and miscellaneous property ties.
Click outside this box to close 197020
This is a scheduled meeting with the FDOT project manager,
the EOR, the District Pavement Design Engineer, and the
Resident Asphalt Specialist to discuss the pavement design
being proposed by the EOR. Topics to be discussed are the
structure, the base, the existing and proposed conditions,
heavy users in the project vicinity, constructability,
cross-slope corrections, variations, cost, TTCP, etc. After
the meeting, the EOR should be able to finalize the pavement
design for sign and seal and concurrence.
Click outside this box to close 197030
The Pavement Design will be submitted to the FDOT PM to upload
into PSEE to start the Pavement Design approval process.
Click outside this box to close 315140
The 90% R/W Control Survey Map stage includes finalizing
all required field books and ensuring all Certified Corner
Reports (CCR’s) have been processed and filed with the
Department of Environmental Protection.
Click outside this box to close 197040
Final approval of the pavement design package will be
completed after the Constructability & MOT Review Meeting,
after all comments have been addressed with the District Roadway
office, and prior to Initial Plans Review. Construction costs
changes associated with the pavement design should be identified
and sent to the FDOT PM, updated in LRE, and quantities reflected
in the Initial Plans.
Click outside this box to close 146010
The title search work is done by FDOT Surveying & Mapping.
The R/W Surveyor is required to submit a property appraisers
map with all properties marked that are affected by the project
(this will not include those properties that are affected by
minor driveway connections only). At this stage of design
development at least 85-95% (if not all) of the affected parcels
are known. Also, after the initial identification of properties
affected, the EOR must keep the Surveyor updated if new properties
are identified and the Surveyor must submit follow up title search
requests.
Click outside this box to close 315040
The 90% R/W Control Survey Map review is a final review
confirming all elements of the previous reviews have been
addressed along with ensuring the survey database, field
books and map are all in agreement. Confirmation of
Certified Corner Reports (CCR) completed and filed with
DEP. Upon acceptance, the 90% R/W Control Survey Map is
placed on hold until the 60% R/W Map review stage. Note:
The next map stage development is the 30% R/W Map.
Click outside this box to close 138010
Starts as a copy of the 90% R/W Control Survey Map and revised
accordingly, i.e. removing surveyor's certification, updating
general notes and changing title blocks. The required TOPOgraphic
elements are merged into the drawing.
Click outside this box to close 262010
An informal gathering (workshop/open house), held at a designated
location, where participants review project related materials,
engage with project team members, and provide comments. Meeting
participants may include individuals, elected/appointed officials,
special interest groups, agency representatives and the general public.
Responses to written comments should be completed and approved by the
PIO office within two weeks from the end of the comment period. Comments
and responses should become part of the Public Engagement Meeting report.
Click outside this box to close 292010
An informal gathering (workshop/open house) held at a designated
location, where participants review project related materials,
engage with project team members, and provide comments. Meeting
participants may include individuals, elected/appointed officials,
special interest groups, agency representatives and the general
public. Responses to written comments should be completed and
approved by the PIO office within two weeks from the end of the
comment period. Comments and responses should become part of the
Public Engagement Meeting report.
Click outside this box to close 311010
The EOR should have the comprehensive Bridge Development
Report (BDR) complete and ready to send to the applicable
offices for review. The BDR shall be submitted to the following
offices for review: State Structures Design Office (as applicable),
FHWA (as applicable), District Structures Design Office, District
Geotechnical Office, District Construction Office, District Structures
Maintenance, District Drainage. This review is done in ERC using the
BDR/BHR Default Reviewer List. The BDR should be approved prior to 60%
plans submittal. Review time will depend on complexity of the structure.
Structures Design may be able to provide an estimate for guidance.
Click outside this box to close 900045
The purpose of the Plans-In-Hand field review is to evaluate
the constructability of the Phase II plans. The FDOT Project
Manager will schedule this meeting at least two (2) weeks prior
to the Phase II submittal date. Required participants should
include: FDOT PM, Consultant PM, a FDOT Roadway Design
representative, Consultant Utility Coordinator, FDOT Utility
PM, FDOT Construction-Design Coordination Group, and FDOT Local Operations Office
Construction PM. If the project has Off-System limits, the
Local Agency(s) Maintenance/Construction representative should
be invited. The team will meet on-site and will walk the corridor
together, looking for missing elements in the plans, conflicts with
utilities and other structures, encroachments, and general
constructability. The Consultant PM is expected to provide a
preliminary set of plans to the FDOT PM at least two (2) days prior
to the Plans in Hand field review, prepare the agenda (if required),
sign-in sheet and meeting minutes.
Click outside this box to close 900040
For Major Projects only. The Initial (Phase II) Design
Team meeting is intended to review the engineer's approach
to the final design of all major elements of the project
and resolve any differences. An agenda will be provided,
and all project review experts will be invited. Utility
owners and Local Agencies are encouraged to attend. At
this meeting, a Scope Debriefing will be held to discuss
changes to the project since the original scope was
negotiated. If the Initial Design Team Meeting is held
outside the District Office a separate Scope Debriefing
Meeting will be needed.
Click outside this box to close 183020
Draft Load Rating Report should be submitted in ERC with 90% Plans.
Summaries (Excel & CADD), brief narrative (i.e. reason for
the rating, assumptions, bridge condition if widening, discussion as
needed), relevant superstructure plan sheets, and calculations. Inputs
should show all strengths and geometry. Prefer PDF with page numbers.
If FEM (finite element model) then provide zip inputs and outputs.
One report per structure. This report to be reviewed by Structures Maintenance. Click outside this box to close 133030
This report contains the geotechnical recommendations for the structures'
foundations and should incorporate any changes based on BDR review
comments. This report is submittefd into ERC with the associated plans.
It is reviewed by FDOT Structures and GeoTechnical Office(s). Click outside this box to close 115030
The 30% Structure Plans provide the basic geometry and preliminary
member sizes of the structural elements. This submittal can be combined
with the BDR for small / minor projects. If the 30% plans are not included
with the BDR submittal, they should be included with the Roadway Phase II submittal in ERC.
Click outside this box to close 106020
This submittal is required at the same time Initial Plans
(Phase II) is submitted to the Department for review. This
includes all the additional design survey done since the
initial mainline design survey database submittal and includes
all the updated MicroStation drawing files. At this time,
basically the majority of the design survey has been completed
and provides sufficient survey data for the EOR to finalize
the right of way requirements needed for the project.
Click outside this box to close 424010
This is an on-site field review of anticipated right of way impacts which should be
accomplished prior to the 60% Mapping Team (Parcel by Parcel) Meeting (Activity Code 9000050).
The purpose of this field review is to identify all proposed take areas and to identify potential
problem take areas that should be avoided or minimized to reduce ROW impacts to the project.
The FDOT Consultant Project Manager, the project EOR and the Right of Way Project Manager will
need to meet on the project to review all anticipated right of way impacts and proposed acquisitions.
The Design Team will need to provide the Right of Way Project Manager an update of the anticipated right of
way needed for the project. You will need to include all real property parcel impacts including potential ponds,
corner clips, strip takes and impacted improvements. The parcel impacts will need to be visualized on an
appropriate exhibit and quantified on the Excel spreadsheet format provided at the Right of Way Kickoff Meeting
or suitable alternative worksheet approved by the Right of Way Cost Estimate Coordinator
Click outside this box to close 450010
The State Transportation Improvement Program (STIP) is a federally
mandated document which must include a listing of projects planned
with federal participation in the next four fiscal years. Each
Metropolitan Planning Organization (MPO) in the state is required
by Florida Statutes to have a Transportation Improvement Program
(TIP) which, as a component of this plan, must include a listing
of projects planned for the next five fiscal years. Federal law
requires each MPO TIP to be included without change in the STIP.
This event ensures the Project is consistent with these two
documents. If the project is not constituent with the TIP/STIP,
the scope of the project significantly changed, or the cost estimate
of the project changed by 2 million dollars (or 70%), the project
will have to go through the MPO verification process. The MPO
verification process can take four (4) to eight (8) weeks. The
point of contact for this event is Government Liaison Administrator.
Click outside this box to close 302010
The EOR will contact the FDOT PM to coordinate the submittal
date, and EOR will send all submittal documents to the FDOT
PM who will upload them to ERC and assign to reviewers.
(Note: Plans should be distributed to local agencies within
the project’s influence, including cities, counties, transit,
etc.) The EOR shall attach a signed Conformance to Quality
Control letter to the submittal. All reviewer comments are
documented in the Electronic Review Comments (ERC) system.
Click outside this box to close 140010
The 30% R/W Map is a copy of the approved 90% R/W Control
Survey Map. At this stage, the topographic improvements
are added. This review confirms the topographic improvements
incorporated along with the revisions required to convert
the R/W Control Survey Map to a right of way map have been
addressed. This map serves as the base exhibit for the Pre-Parcel
Review meeting where the Engineer of Record (EOR) presents the
proposed right of way requirements for the project. The offices
of Design, Right of Way, Legal, and Survey & Mapping are present
to address any concerns or make recommendations on the adjustment
of the final right of way requirements.
Click outside this box to close 900090
This meeting is scheduled by the FDOT PM and includes the Consultant PM, EOR,
Consultant Surveyor, District Right of Way Surveyor, FDOT Mapping Reviewer,
FDOT Mapping/ Title Specialist, FDOT R/W Special Project Coordinator,
FDOT Utilities PM, Consultant Utilities Coordinator, FDOT R/W Cost Estimates,
FDOT Roadway Design Engineer, and FDOT Legal (eminent domain). At the meeting,
a cursory review is performed parcel by parcel of the proposed R/W fee takes,
easements and all driveway tie-ins that extend beyond the existing and/or proposed
right of way line. This meeting is a proactive approach to fine tune requirements
to provide the most cost-effective requirements possible. Click outside this box to close 264010
The CONSULTANT shall transmit the Approved Phase II Utility Contact Package to all UAOs. The CONSULTANT shall
schedule (time and place) for a Utility Design Meeting, notify participants,
and conduct the Meeting with all affected UAOs.
Click outside this box to close 264210
This is only for instances wher edesign changes occurred ad=fter approved Phase II Utility Contact.
The CONSULTANT shall transmit the Revised Utility Contact Package to all UAOs.
If needed, the CONSULTANT shall schedule an additional Utility Design Meeting.
Click outside this box to close 373010
This is a subsequent pavement type selection report submittal
activity that is required for applicable projects. This is
the third submittal generally required with the initial report
being done during the PD&E phase of the project and the
second submittal having taken place during the phase I
development of the project. This submittal should be made to
the District Pavement Design Engineer who will QA the document,
get District Design Engineer approval and then transmit it to
the State Pavement Design Engineer in Central Office for further
processing and submittal to Industry for final review and comment.
The purpose of this third report is to verify the assumptions
used in the previously submitted reports and to provide a more
comprehensive design and analysis based on the information current
at the time of this third and final submittal. Please refer to the
Department's current Pavement Type Selection Manual for additional
information and description of applicable projects.
Click outside this box to close 302030
This is the timeframe that the EOR responds to comments from
the Initial Plans (PH II) review. All reviewer comments are
documented in the Electronic Review Comments (ERC) system.
The FDOT PM should work with all review units to ensure reviews
are performed by the due date. The EOR should respond to each
comment individually and the reviewer will accept, reject or
request additional information. Unresolved comments will require
coordination with the reviewer, EOR and FDOT PM. Any unresolved
comments should be addressed until all parties are satisfied,
to include but not limited to: phone conferences, interactive
review, etc. The FDOT PM is responsible to monitor the process
until comments are successfully resolved.
Click outside this box to close 238020
This line item is placed in the schedule as a reminder to
the FDOT Project Manager to perform an interim grade in
the FDOT Consultant Evaluation System. This is utilized
so that the Consultant Firm has some feedback as to their
current performance on the project. Any questions
concerning the Evaluation System can be addressed by D5
Consultant Project Management – CES Administrator.
Click outside this box to close 138030
EOR adjusts the design to address right of way requirement
revisions based upon the outcome of the Pre-Parcel Review
Meeting and the Initial Plans Review.
Click outside this box to close 302040
This is the time frame that the EOR must update the Initial
Plans (Phase II) with the comments and changes received
from the Initial Plans (PH II) Review. The District Utility
Office requires that the plans be updated prior to making
utility contacts.
Click outside this box to close 145010
This process outlines the steps necessary to prepare,
review and submit permits to appropriate agencies. It
includes completion of permit application, relevant
attachments (i.e. project location map, aerials, affidavit
of ownership, pictures, additional technical analysis, etc.),
and cover letter with project description. A 12-step process
is given in the attached link.
Click outside this box to close 267010
The FDOT Railroad Coordinator contacts railroad representatives
advising them of active projects within or near their railroad
facilities. This contact is done in writing and includes a project
description and projected fiscal year funding information.
Click outside this box to close 131020
This report will address the Phase II review comments and any new
geotechnical issues. This report is included in the 90% plans submittal. Click outside this box to close 359010
The FDOT Project Manager will confirm local (County/City)
support from the designated local (County/City) contact
obtained during the Stakeholders meeting or ‘Contact Local
Agencies’. The locals should have been provided with the
submittal in the ERC. The submittal may have to be electronically
delivered, via email or FTA, if the locals are not in the ERC
system. To confirm local support, the FDOT Project Manager
should contact the locals, email or phone, after 'Respond to
Comments' is complete and be sure any additional comments or
concerns have been addressed. Confirmation should be obtained
in writing via email, meeting minutes, etc.
Click outside this box to close 322020
Consultant Designer/EOR submits final right of way
requirements and the Limits of Construction (LOC) to
the R/W Surveyor & Mapper (S&M). The operative word here is FINAL.
Click outside this box to close 307010
The 30% Structure Plans shall be submitted by the FDOT PM in ERC for
review by: District Structures Design, District Geotechnical, District Construction,
District Structures Maintenance, District Drainage and District Utilities. For Category
II structures Central Office Structures Design will also perform a review. The
FDOT PM should contact Structures Design for the State Structures contact. For federal
oversight projects FHWA will also perform a review. Click outside this box to close 900050
The intent of this meeting is to do a parcel by parcel review of the right
of way requirements necessary for the construction and maintenance of the project
including driveway tie-ins. The Consultant Surveyor overlays the R/W requirements
and LOC provided by the EOR on the R/W Map and provides sets at the meeting. The
purpose is to address all final comments and establish the final right of way
requirement needs. Meeting invitees are the same as Pre-Parcel Meeting invitees.
The parcel revision tracking form (aka. R/W Change Tracking Form) must be submitted
to the Department no more than three (3) working days after the meeting.\
ALL PARCEL NUMBERS MUST BE ISSUED BY THE FDOT SURVEYING & MAPPING TITLE UNIT. Click outside this box to close 329010
Environmental evaluations are required on all project during the Design Phase.
The level of assessment and documentation depends on the type of project.
Coordination with EMO will commence with the Plans Review via ERC.
Click outside this box to close 139010
Parent tract properties, based on complete title search
work or last deed of record if title work is not complete,
for all proposed R/W take areas finalized and the requirements
and limits of construction are shown graphically. The Table
of Ownership sheet is started at this stage. A team field
review is required at this stage to ensure all TOPOgraphic
elements required for take areas are shown on the map.
Click outside this box to close 264450
On or before this date the Consultant shall transmit a complete set
of Plans for Plans Update, to each UAO, with a conflict matrix. The CONSULTANT
shall schedule (time and place) for a Utility Design Meeting, notify participants,
and conduct the Meeting with all affected UAO(s).
Click outside this box to close 264050
Description will be updated soon.
Click outside this box to close 359030
The FDOT Project Manager will confirm local support
after Responses to Comments are complete for the updated
plans review. Prior to and during Review and
Responses to Comments, the FDOT Project Manager should
be coordinating with Local Agencies to confirm local
support for the project. Local support should be
confirmed prior to proceeding to Production.
Click outside this box to close 222020
All updated permits necessary for construction of the
project have been obtained. These permits include but
are not limited to water management district permits,
ACOE, Coast Guard, FFWCC, etc.
Click outside this box to close 113030
This is the Final Plans (PH III) development stage.
All Initial Plans (PH II) comments have been addressed
or resolved and are reflected in the plans as appropriate.
Click outside this box to close 329020
An environmental certification is required for all projects. For minor project,
once the Environmental Permits Clear document is received, submit an email to the
Environmental Management Office and include the following: FPID#, detailed project
description which includes the work activities to be performed and if the project
is state or federally funded. For major projects, the environmental certification
will be supplied after a construction advertisement evaluation has been approved.
Click outside this box to close 298060
This is the third of four scheduled Right of Way cost
estimate updates. The FDOT Consultant Project Manager
and the EOR will need to provide the FDOT R/W Cost
Estimates/Design Support team an update of the
anticipated right of way needed for the project. All
real property parcel impacts need to be accounted for,
including potential ponds, corner clips, and strip takes.
The impacts will be visualized on an appropriate exhibit
and quantified on the form provided at the Right of Way
Kickoff Meeting or suitable alternative worksheet approved
by the Right of Way Cost Estimate Coordinator.
Click outside this box to close 133040
This report will address the 30% review comments and any new
structural issues. It is included with the Phase II plan submittal in ERC.
Click outside this box to close 115040
The purpose of this the 60% substructure submittal to ERC
is to communicate essential project information to the Geotechnical
and Hydraulic Engineers to ensure that all remaining calculations
can be performed using actual structural shapes, loads and dimensions.
Plan sheets required for this submittal include: Plan & Elevation,
Bridge Hydraulics Recommendation Sheet, Boring Logs, Foundation Layout,
Substructure Plans and draft technical specifications.
Click outside this box to close 272010
After the Submittal of Permit Application, the Environmental
Permits Office will monitor the progress of all permits
under agency review. The Consultant will respond to all
requests for additional information from the regulatory
agencies and report to the Environmental Permits Office.
The Environmental Permits Office will review all additional
information prior to the Consult official submittal to the
agencies.
Click outside this box to close 308010
The 60% Substructure Plans shall be submitted into ERC by the
FDOT PM for review by District Structures Design, District Geotechnical,
District Construction, District Structures Maintenance, District Drainage
and District Utilities. All bridges have a 60% substructure review.
For Category II structures, the FDM Section 121.11.2 (2) will list additional
reviews needed. Besides district staff, Central Office Structures Design
will also perform a review. The FDOT PM should contact the District Structures
Design Office for the State Structures contact. For federal oversight projects
FHWA will also perform a review.
Click outside this box to close 279010
The purpose of this memo is to inform the FDOT Project
Manager of any railroad involvement within the project
limits. This memo is issued by the FDOT Railroad
Coordinator and sent to the FDOT Project Manager for
further distribution.
Click outside this box to close 359052
This meeting, which is held 365 days after the 2nd
Annual Local Agency Contact Meeting, is held to update
Local Agencies on the status of the project. The
time spent while the project is "on the shelf"
or in Right of Way can be periods of leadership changes,
priority changes and continued development within the
Local Agency. During these periods, the Project
Manager should make annual contact with the Local
Agencies advising of the status of the project and
inquiring if there are any changes the Department should
be aware of. The Local Government Partnering
Meetings are a good opportunity to perform this annual
contact. Depending on the feedback received,
additional public involvement efforts may be necessary
to ensure continued support and consensus of the
project.
Click outside this box to close 212010
The date that the Contract File (inclusive of plans,
specifications, etc) are transmitted to Tallahassee, so
that Contracts Office can advertise the project,
allowing contractors to bid.
Click outside this box to close 370010
The date that the Contract File (inclusive of plans,
specifications, etc) are transmitted to District
Contracts, so that Contracts Office can advertise the
project, allowing contractors to bid.
Click outside this box to close 359060
Prior to letting, the Local Agencies should be contacted
once again. The purpose of this final design
contact would be to inform them of the project moving to
letting and construction, review the final outcome of
Local Agency issues, and provide contact information for
the Resident Construction Office that will be
responsible for the administration of the construction
and continuing public involvement efforts for the
Department. Specifically, the contact information
for the Resident Engineer and Resident's Public
Information Specialist should be provided to the Local
Agencies. The recommended approach for this final
contact is a telephone call to the primary project
contact for each Local Agency, followed by an email to
all Local Agency personnel involved in the project.
Include the Resident office staff in this email as they
(the Resident Office) will again contact locals
immediately prior to the Contractor beginning
construction operations.
Click outside this box to close 280010
This is the date set by work program for the Department
to open bid proposals from Contractors. This date
typically occurs approximately 3 months after the
production date.
Click outside this box to close 236010
This line item is placed in the schedule as a reminder
to the FDOT Project Manager to perform a final grade in
the FDOT Consultant Grading System. This is utilized so
that the Consultant Firm has some feedback as to their
overall performance on the project. Any questions
concerning the Grading System can be addressed by the
FDOT Professional Services unit (Duration: 62 Calendar
Days).
Click outside this box to close 971020
Pass the Torch Meeting is intended to transfer all
relevant production project information to construction.
Right of Way is responsible for scheduling these
meetings within two weeks of the project letting date.
Representatives should include the Design project
manager, the consultant, the appraiser, R/W general
consultant, R/W agents, Legal, Access Management
representative, utilities and construction. The
agenda is a parcel by parcel discussion of the issues
and commitments made from the PD&E, Design, Right of
Way, Utilities, and Legal. Construction is
provided with a notebook containing parcel ownership
information, aerial photographs, cure plans and hard
copies of right of entries, final judgments, deeds,
easements, etc. A right of way contact is
designated for continued support throughout the project
construction. A right of way team leader chairs
the meeting and provides the minutes.
Click outside this box to close 140020
The 60% R/W Map sheets (Cover, Key, Detail, Reference Point)
and the partially completed Table of Ownership (TAB) sheet
are required for this review. This submittal also includes
the right of way requirements graphically shown, parcel
bubbles and numbers, Limits of Construction and complete
geometry on parent tract properties. Click outside this box to close 133050
This report will address the 60% review comments and any new
structural issues including walls, etc. It is submitted along
with the Phase III plans into ERC for review. Click outside this box to close 115050
The 90% Structures Plans should be submitted to ERC with the Phase
III Roadway Plans, with the same reviewers as the BDR. The EOR
should have resolved all 30% and 60% structures plans review comments
and developed the plans for completion. This submittal shall include
the completed plans, Summary of Pay Items (quantities), design calculations,
Geotechnical Report, Addendums to Hydraulic Report, and TSP’s if appropriate.
If an Independent Peer Review is required, it will be done at the same time as this review. Click outside this box to close 315050
FDOT Surveying & Mapping unit requests Final Delivery of
the R/W Control Survey Map package which includes MYLARS
of all map sheets along with the required number of certified
paper copies and other supporting documentation (i.e., final
field books). This deliverable typically coincides with
acceptance of the 60% R/W Map.
Click outside this box to close 146110
This activity is performed by FDOT Surveying & Mapping
during the 90% R/W Map stage. Updated title searches are
provided to the R/W Surveyor as they are finalized.
Click outside this box to close 139020
Includes all map sheets (Cover, Key, Detail, Reference Point,
Table of Ownership) and legal descriptions on all acquisition
areas. Address any title changes reflected in the title search
updates. All existing easements are added to the R/W Map based
on the title search. Geometry on proposed acquisition areas and
remainder parent tract areas are finalized. The R/W Surveyor
sends one set of 90% R/W Maps to the EOR for a comparison review
against the design plans to ensure the existing and/or proposed
R/W agree and that sufficient R/W has been established for project
construction and future maintenance. If a TIITF Easement is part
of the scope, the sketch and legal are also submitted for review.
Click outside this box to close 325010
See explanation of TIITF under the TIITF Determination
activity #325020. If required, the preparation of the
sketch and legal description begins at the same time as
the 90% R/W Map stage. Survey field work required to
support the certified sketch was completed under the R/W
Survey activity.
Click outside this box to close 971010
Right-of-way appraisal, acquisition and relocation
administrators field trip the project; team members
are identified; general consultant for appraisal support
is selected; parcel summary sheets are drafted.
Click outside this box to close 140030
Includes all map sheets (Cover, Key, Detail, Reference Point,
Table of Ownership) and legal descriptions on all acquisition
areas. A complete geometric review is done for all parcels and
parent tract remainders to verify accuracy. All existing
easements within acquisition areas are shown along with the
holder's name, recording data and width, if uniform. For blanket
easement(s), the holder's name and recording data is required to
be shown near the acquisition area(s). The Table of Ownership
(TAB Sheet) is reviewed for accuracy and completeness. Parcel
and parent tract descriptions are reviewed by the FDOT Mapping/
Title Specialist in coordination with the FDOT Surveying &
Mapping Project Manager and any comments are addressed. Upon
acceptance of the 90% R/W Map by FDOT staff, the R/W Control
Survey Map Final Deliverable with MYLARS, certified field book(s),
and certified database is requested.
Click outside this box to close 303010
The EOR will send all submittal documents to the FDOT PM
who will upload them to ERC and assign to reviewers.
(Note: Plans should be distributed to local agencies within
the project’s influence, including cities, counties, transit,
etc.) The EOR shall attach a signed Conformance to Quality
Control letter to the submittal. All reviewer comments are
documented in the Electronic Review Comments (ERC) system.
At this stage, the design of the project should be complete,
with all major cost pay items loaded and quantified.
Click outside this box to close 184010
Submit sealed Load Rating Report with Final Contract Plans
(100% Plans if Design-Build) into ERC. This report is reviewed
by Stuctures Design and Structures Maintenance. This report is
also required with the 90% Structures Plans submittal. To submit,
seal both summaries. PDF or ZIP formats are preferred. One report
per structure. Once approvals are given, a finalized Load Rating
- Post Construction Sheet is sent to the FDOT Structures Maintenance
Engineer for the project files.
Click outside this box to close 308020
The 90% Structure Plans shall be submitted into ERC by the
FDOT PM with Phase II Plans. Reviewers include Structures
Design, Geotechnical, District Construction, Structures Maintenance,
and Utilities. For Category II structures the State Structures Design
Office will also perform a review. The FDOT PM should contact the
District Structures Design Office for the State Structures contact.
For Federal Oversight projects FHWA will also perform a review
Click outside this box to close 139030
This map stage should be limited to addressing minor
review comments, if any, from the 90% R/W Map and Legal
Description review, and addressing all final title changes,
if any, based on the updated title searches. Click outside this box to close 303030
This is the timeframe that the EOR responds to comments from
the Final Plans (PH III) review. All reviewer comments are
documented in the Electronic Review Comments (ERC) system.
The FDOT PM should work with all review units to ensure
reviews are performed by the due date. The EOR shall respond
to each comment individually and the reviewer will accept,
reject or request additional information. Unresolved
comments will require coordination with the reviewer, EOR
and FDOT PM. Any unresolved comments should be addressed
until all parties are satisfied. The FDOT PM is responsible
to monitor the process until comments are successfully resolved.
Click outside this box to close 238030
This line item is placed in the schedule as a reminder to
the FDOT Project Manager to perform an interim grade in the
FDOT Consultant Grading System. This is utilized so that the
Consultant Firm has some feedback as to their current performance
on the project. Any questions concerning the Grading System
can be addressed by D5 Consultant Project Management – CES
Administrator.
Click outside this box to close 238040
This line item is placed in the schedule as a reminder
to the FDOT Project Manager to perform an interim grade
in the FDOT Consultant Grading System. This is
utilized so that the Consultant Firm has some feedback
as to their current performance on the project.
Any questions concerning the Grading System can be
addressed by the FDOT Professional Services unit
(Duration: 62 Calendar Days).
Click outside this box to close 140040
If the 90% R/W Map and legal description review comments
are minor and there are no title changes, this review
stage may be waived by the District Surveyor or his/her
designee.
Click outside this box to close 264040
Prior to this date, the Utility Coordinator (UC) will submit the
reviewed utility documents with their and the EOR QA/QC Comments
to appropriate FDOT departments, who will then complete their review
and comments of the documents. Click outside this box to close 115060
The EOR shall make all authorized changes necessary to complete the plans and
technical special provisions (TSP) after resolution of the 90% comments. The
EOR shall also submit a list of changes made to the plans or specifications that
were not directly related to the 90% review comments. The FDOT will submit the
100% Structures Plans into ERC with the Final Plan submittal. Click outside this box to close 359020
The FDOT Project Manager will confirm local (County/City)
support from same the designated local (County/City) contact
used during Initial Plans after responses to comments are
complete for the Final Plans review. Local support should
be confirmed prior to proceeding to 100% plans coordination.
Confirmation should be obtained in writing via email, meeting
minutes, etc.
Click outside this box to close 310010
This phase is designated to complete the final touches
on the design plans and update quantities based on the
agreed upon comment resolutions to the Final (Phase III)
Plans review. The EOR shall provide the updated utility
adjustment sheets and/or roadway plan sheets that show
the utilities and all applicable component plan sheets
(i.e., cross sections, drainage structures, signal, etc.)
to the Utility Coordinator and the District Utility Office
for verification that the utility information has been
plotted correctly. The PM will verify concurrence to
all comments/responses from the reviewers. No additional
comments are being requested, just confirmation that the
appropriate changes were made. The Engineer of Record
will demonstrate to the FDOT that the plans and quantities
were updated appropriately.
Click outside this box to close 266010
On or before this date, the Consultant shall submit the certification
package to the District Utility Office (DUO). Click outside this box to close 157010
R/W Map MYLARS and certified legal descriptions (certified
TIITF Sketch, if applicable) are finalized and received by
FDOT Surveying & Mapping. The EOR provides the R/W Change
Tracking Form and a Compatibility Letter that confirms the r/w
shown on the maps is sufficient to build the project and is
comparable to the r/w requirements denoted on the design plans.
Click outside this box to close 144010
This activity is done by FDOT Surveying & Mapping.
Includes final analysis of the title search, flag sheets
and title documents prepared. Map sets and individual
sheets printed and outlined in color, and parcel folders
prepared.
Click outside this box to close 133060
This report shall include final bridge foundation and wall analyses.
Click outside this box to close 310050
This time frame is established so the Engineer of Record
can demonstrate to the FDOT that the plans were updated
according to the resolutions from the Final (Phase III)
Plans and are now final.
Click outside this box to close 268010
Maps, Title Documents and Parcel Folders delivered to
R/W Administration. This is normally the last Survey &
Mapping task unless updates or revisions are required.
(See Update Survey, Activity 139060 and Update R/W Map,
139070). However, Title will update documents as needed
until negotiations/suits are finalized.
Click outside this box to close 349010
This activity represents the execution of any service
contracts for the development of real estate appraisals
or other related support activities necessary for the
acquisition of right of way parcels.
Click outside this box to close 208010
This defines the time period which allows the FDOT to hire a consultant fee appraiser to perform appraisal services.
During this period, the FDOT Deputy District Right of Way Manager – Valuation and the Appraisal Administrator review the project, discuss
a general Scope of Services and determine appropriate contracting services to develop real property appraisals.
The appraisal services are contracted with a Districtwide Contract. Click outside this box to close 131030
This signed and sealed report will address the Final Plans
(Phase III) review comments.
Click outside this box to close 201010
The development of the design plans is completed.
All comments from prior phase reviews have been
resolved and the plans have all appropriate changes
incorporated. These plans are ready to be signed and
sealed. Quantities are updated by the EOR and an updated
construction cost estimate is initiated.
Click outside this box to close 106040
This submittal is required at the same time plans are complete.
The submittal incorporates all the remaining design survey done
for the project and includes all the required final MicroStation
drawings, the appropriate Surveyor’s report(s) and the EOR's
letter of satisfaction of the design survey product.
Click outside this box to close 298090
This is the final of four scheduled Right of Way
cost estimate updates. The FDOT Consultant Project
Manager and the EOR will provide the FDOT R/W Cost
Estimates/Design Support team an update of the
anticipated right of way needed for the project.
The Right of Way exhibits include all real property
parcel impacts including potential ponds, corner
clips, and strip takes. The impacts will be visualized
on an appropriate exhibit and quantified on the form
provided at the Right of Way Kickoff Meeting or
suitable alternative worksheet approved by the Right
of Way Cost Estimate Coordinator.
Click outside this box to close 222010
All Environmental Permits necessary for Letting of the
project have been obtained. These permits include water
management districts, Army Corps of Engineers (ACOE),
Coast Guard, Florida Department of Environmental Protection
(FDEP). The “All Permits Clear” memo will be issued 6
weeks prior to production.
Click outside this box to close 120010
The appraisal activity is the period of time allotted for
the submission of all real estate appraisals required for
the initial negotiation of the identified right-of-way project.
Click outside this box to close 143010
The time period to complete the review of the real estate appraisals by FDOT Appraisal Review staff or Consultant Review Appraisers.
The appraisals are approved for use in the negotiations to purchase required right-of-way for a project. Click outside this box to close 129010
The time period for providing advisory services and/or
financial aid to persons and businesses displaced by a
public program to assist in relocating to available residential
replacement dwellings and non-residential replacement sites.
These activities are necessary in order to be in compliance
with federal regulations (The Uniform Relocation Assistance
and Real Property Acquisition Policies Act of 1970, as amended).
Click outside this box to close 121010
The time period for presenting offers and negotiating
with property owners/representatives to purchase right
of way parcels. The initial offer is based on approved
compensation determined by the review appraiser. The
R/W agent attempts to negotiate a settlement agreement
that will allow the parcel to be closed without condemnation.
The negotiation end date is the date of the final order of
taking for the project.
Click outside this box to close 359050
This meeting is held when a project does not immediately
go to construction at the conclusion of design.
The time spent while the project is "on the
shelf" or in Right of Way, can be periods of
leadership changes, priority changes or continued
development within the Local Agencies. During
these periods, the Project Manager should make annual
contact with the local agencies, advising of the status
and inquiring if there are any changes the Department
should be aware of. The Local Agency Partnering
Meetings are a good opportunity to perform this annual
contact. Depending on the feedback received,
additional public involvement efforts may be necessary
to ensure continued support and consensus of the
project.
Click outside this box to close 240010
This date is when all unacquired parcels on a project
are to be prepared and submitted for eminent domain action.
Click outside this box to close 273010
The date by which the final order of taking must take
place for the project to be cleared by the scheduled
Right-of-Way Certification date.
Click outside this box to close 125010
As soon as right of way parcels are acquired and FDOT has physical possession, any improvements on the parcels are cleared. Click outside this box to close 359051
This meeting which is held 365 days after the Initial
Annual Local Agency Contact Meeting, to update Local
Agencies on the status of the project. The time
spent while the project is "on the shelf" or
in Right of Way can be periods of leadership changes,
priority changes and continued development within the
local agencies. During these periods, the Project
Manager should make annual contact with the Local Agency
advising of the status and inquiring if there are any
changes the Department should be aware of. The
Local Agency Partnering Meetings are a good opportunity
to perform this annual contact. Depending on the
feedback received, additional public involvement efforts
may be necessary to ensure continued support and
consensus of the project.
Click outside this box to close 255010
The project is certified clear for construction when FDOT has title to all the
right-of-way, relocation is complete, all improvements have been cleared,
and there is construction funding and a letting date.
Click outside this box to close 933010
All items should be complete prior to this date
including contract time, utility certification,
permits cleared, R/W cleared, plans completed,
JPA's completed, R/R coordination cleared, FAA
coordination completed, etc. The FDOT Project
Manager should complete the Transmittal of Plans,
Specifications, and Estimates Package (Form 131-A)
and the Contract File Index (Form 131-B). Both
can be found in FDM. Once the whole package is
compiled, the FDOT PM should send an e-mail to the
DCPME stating that the project is now DCPME ready
and can be entered into specs if needed. Consultant
should include in the Final Deliverable/Production
Submittal a ZIP file or CD that includes all the
signed and sealed design reports. This includes
(but is not limited to): Structures Reports, Geotech
Reports, Design Drainage Reports, Design Traffic
Reports, etc. If the DCPME determines a QAR of the
project needs to be performed this information shall
be transmitted to the Quality Assurance and Design
Services Manager for review.
Click outside this box to close 171010
The period of time, measured in calendar days, allowed
for completion of the construction contract including
all holidays and special events.
FDOT PM to coordinate contract time with the following distribution email:
D5Construction-DesignCoordinationGroup@dot.state.fl.us
Click outside this box to close 310020
This is a communication meeting between the Project
Manager, EOR, EDelivery person (CADD In-House/Consultant),
Estimates, Construction, and Specs to discuss any
outstanding issues and commit to dates for the Production
and Final Submittals to Specs. Click outside this box to close 204010
This is the committed delivery date for final plans,
certifications (utilities, permits, R/W, environmental,
etc.) and Agreements (LFA’s, JPA’s etc.) to the Specs
and Estimates Department. The assigned Construction
Contract number is placed on the Key Sheet(s).
Click outside this box to close 226010
Submittal(s) consisting of the Final Plans,
Specifications and Estimate along with any other
contract and transmittal documents. PS&E Submittals are
numbered consecutively and re-submittals are required
until the project is accepted by the District Program
Management Office.
Click outside this box to close 242010
This is the time between electronic deliverables going
to Specs, at which time Specs and CADD will do their
review, and the start of Production (or earlier) and
ending at Fully Electronic Transmittals Due To
Tallahassee or District Contracts
Click outside this box to close 359025
This meeting should take place 4 months prior to the
Plans Update Phase. For this meeting the project
manager will re-contact the City and County Manager's
office to inform them of the beginning of the design
update phase, and to inquire as to which City/County
Departments need to be included on project
correspondence. A summary of the scope of the
project should be provided and invitations to a Plans
Update Design Team Meeting should be extended. If
the local agencies have new or modified design request,
they should also be discussed at this meeting.
Click outside this box to close 220010
The Plans Update Design Team Meeting is intended to
review the designer's approach to the final updated
design of all major elements of the project and resolve
any differences. Utility owners and local agency
representatives are encouraged to attend.
Click outside this box to close 164020
After negotiations for plans update phase is completed,
this is the time period where the FDOT Project Manager,
Negotiator, and Prime Consultant gather all the
finalized documents (scope of services, units, and staff
man-hour estimates, audit packages, etc.) necessary for
developing a complete contract package. Negotiator to
submit complete package to Professional Services for
successful execution.
Click outside this box to close 220420
The plans update process begins when final contract plans,
specification and estimates (PS&E) package has been on
the shelf for any significant period (approximately nine
months). The update process depends on the type of project,
the adequacy and appropriateness of the original design
controls and standards, and the original scope and objectives.
The extent of the update process should be determined based
on both engineering and management input. Contract plans
must be reviewed for current requirements, including standard
plans, specifications, pay items, design criteria, target
speed, typical section changes, design documentation updates,
and design analysis evaluation needs. Agreements with outside
entities such as Utility/Agency Owners (UAOs), maintaining
agencies and local agencies must be reviewed.
Click outside this box to close 220030
This review begins once updated plans are complete. The
Consultant PM should use the transmittal forms located
on the Department's Electronic Review Comments (ERC)
website for this submittal (note: plans should be
distributed to Local Agencies and public transportation
entities within the project's influence). In addition to
the submittal form, the consultant shall attach a signed
Conformance to Quality Control letter. At this stage,
the design of the project should be complete, with all
major cost pay items loaded and quantified. After the
phase review ends, the consultant should prepare
responses within 2 weeks of the end date and submit
those responses for concurrence from the Department. A
signed Concurrence for Review letter is a requirement
before proceeding to 100% Plans Coordination.
Click outside this box to close 139060
Update Survey necessary for designers and engineers of
record to utilize during plans update phase.
Click outside this box to close 139070
Update R/W Map if there is a substantial delay from the
R/W Map Complete activity to Docs to R/W activity for
the project (r/w acquisition not funded or several years
out). Determination as to whether this activity is
required or not on any given project is made by the
District Surveyor.
Click outside this box to close 125030
Description will be updated soon.
Click outside this box to close 272040
The time period for verifying permits are not expired or
are close to expiring and require permit extensions. If
the permit has expired, the Consultant is responsible
for coordinating with the D5 Permit Coordinator and
assisting with filing for a permit extension(s).
Click outside this box to close 900080
Project Manager Schedules a meeting with their consultant and District Traffic Operations,
as identified in the agenda. The Consultant reviews the agenda and prepares accordingly
for the meeting. If there are items the Consultant is not prepared for the meeting should
be rescheduled after they have collected and organized the needed information from coordination
and field review.
Click outside this box to close
District Five Consultant Project Management Schedule Dictionary
Activity
Activity Name
Desc
Category
Predecessor
Activities
Successor
Activities
Links
971130
PD&E Pass the Torch Meeting / Begin CAP
6- Project Initiation / Negotiations
- Stage I Scope Review
- Attendee List: PD&E Pass the Torch
- PM Handbook (See Part 2, Chapter 3)
299010
Request Authorization PH 31 Funds
6- Project Initiation / Negotiations
- Stage I Scope Review
164010
Stage I Scope Review
6- Project Initiation / Negotiations
- PD&E Pass the Torch Meeting / Begin CAP
- Stage II Scope Evaluation
- Design Standard Scope of Services (SOS)
230130
Stage II Scope Evaluation
6- Project Initiation / Negotiations
- Stage I Scope Review
- Send AD Request Form/Scope to PSU
- Negotiate Staff Hours
- Design Standard Scope of Services (SOS)
231010
Send AD Request Form/Scope to PSU
6- Project Initiation / Negotiations
- Stage II Scope Evaulation
- Project Execution/PE Begin
- Professional Services Advertisement Request Form
(connection to FDOT network/VPN is needed)
230140
Stage III (Final) Scope Development
6- Project Initiation / Negotiations
- Negotiate Staff Hours
-
232010
Advertisement Post
6- Project Initiation / Negotiations
- Send AD Request Form/Scope to PSU
- Final Selection Meeting
- Current Professional Services Advertisements
402010
Final Selection Meeting
9 - Project Management
- Advertisement Post
- Finalize Scope of Services
900020
Finalize Scope of Services
6- Project Initiation / Negotiations
- Final Selection Meeting
- Negotiate Staff Hours
- Staff Hour Estimation Guidelines (SHE)
164030
Negotiate Staff Hours
6- Project Initiation / Negotiations
- Finalize Scope of Services
- Encumber Phase 32 Funds (Major)
- Encumber Phase 32 Funds (Minor)
- Stage III (Final) Scope Development
- Contracts Negotiations Handbook
Surveying Units and Exhibit
- Staff Hour Estimation Guidelines (SHE)
- Advisor and Meeting Spreadsheet (Not in Dictionary)
(Contact one of our Contract Managers for info needed)
233020
Encumber Phase 32 Funds (Minor)
6- Project Initiation / Negotiations
- Negotiate Staff Hours
- Project Execution/PE Begin
233010
Encumber Phase 32 Funds (Major)
6- Project Initiation / Negotiations
- Negotiate Staff Hours
- Project Execution/PE Begin
263020
LDCA Approved
6- Project Initiation / Negotiations
- Project Kickoff Meeting
- Initial Plans Review (Phase II)
- PD&E Manual
250010
Project Execution/PE Begin
6- Project Initiation / Negotiations
- LDCA Approved
- Encumber Phase 32 Funds (Minor)
- Project Kickoff Meeting
- Build Schedule
113005
Design Analysis Evaluation
3- Plans Development/Project Management
- Project Execution/PE Begin
- Initial Plans (Phase II)
367010
Exceptions/Variations (Include Utility Design Alternatives)
3- Plans Development/Project Management
- Project Kickoff Meeting
- Approved Exceptions/Variations and Submittal of Utility Design Alternatives
900030
Project Kickoff Meeting
6- Project Initiation / Negotiations
- Project Execution/PE Begin
- Build Schedule
- Develop CAP Strategy
- Coring
- PNC Coordinates
- Order Design Traffic
- Exceptions/Variations (Include Utility Design Alternatives)
- Stakeholders Meeting
- TIITF Determination
- R/W Estimate - Scope
- Design Survey
- Survey Alignment
- R/W Survey
Schedule and Department Expectations
-
Project Kickoff Sheet
(connection to FDOT network/VPN is needed)
-
CPM Project Kickoff Agenda
290010
Develop CAP Strategy
9- Project Management
- Project Execution/PE Begin
- Build Schedule
- Project Kickoff Meeting
359040
Contact Local Agency
8-Stakeholder Coordination/Public Involvement
- Encumber Phase 32 Funds (Major)
- Stakeholders Meeting
- Agency Contact Letter
325020
TIITF Determination
7- Survey, Mapping, & Coordination
- Project Execution/PE Begin
- Prepare TIITF Package
- State Lands - Survey & Mapping
Section 10.3 Right of Way Manual
900010
Build Schedule
6- Project Initiation / Negotiations
- Project Execution/PE Begin
- Project Kickoff Meeting
233030
Encumber Phase 32 funds for S/A (Plans Update)
6- Project Initiation / Negotiations
- Negotiate Staff Hours
- S/A for Plans Update
- D5 WORK PROGRAM REQUEST FORM
(connection to FDOT network/VPN is needed)
170050
PNC Coordinates
7- Survey, Mapping, & Coordination
- Project Execution/PE Begin
- PNC Database
- Mainline Design Survey Database Submittal
294010
Typical Section Developed
3 - Plans Development/Project Management
- Project Execution/PE Begin
- Typical Section Submitted
106210
Survey Alignment
7- Survey, Mapping, & Coordination
- Project Execution/PE Begin
- Survey Alignment Review
170010
R/W Survey
7- Survey, Mapping, & Coordination
- Project Execution/PE Begin
- 90% R/W Control Survey Map
106010
Design Survey
7- Survey, Mapping, & Coordination
- Project Execution/PE Begin
- Mainline Design Survey Database Submittal
- FDOT Surveying & Mapping Office
424020
Right of Way Kick-off Meeting
1- Right of Way Acquisition
- R/W Estimate - Scope
-
Right of Way Kickoff Meeting Agenda
900070
Stakeholders Meeting
8- Stakeholder Coordination / Public Involvement
- Project Kickoff Meeting
- Contact Local Agency
- Line & Grade (Phase I)
-
Agenda: Stakeholders Meeting
-
Stakeholder Invitees
256010
Order Design Traffic
3- Plans Development/Project Management
- Project Kickoff Meeting
- Design Traffic Received
- Traffic Request Portal
(connection to FDOT network/VPN or FDOT logon credential is needed)
933020
Define Local Agreement Issues
8-Stakeholder Coordination/Public Involvement
- Stakeholders Meeting
- Initial Plans Review (Phase II)
- Initial Design Team Meeting (Phase II)
298010
R/W Estimate - Scope
1- Right of Way Acquisition
- Project Kickoff Meeting
- Right of Way Kick-off Meeting
- Line & Grade (Phase I)
- Project Information for Right of Way Cost Estimate
(connection to FDOT network/VPN is needed)
264000
Advance Utility Notification
- Utility Contact (minor and plans update)
2- Utilities
- Build Schedule
- Project Execution/PE Begin
- Utility Contact (minor and plans update)
- Utility Contact 2nd
- Utility Contact (major projects - UWS)
304010
Coring
3- Plans Development/Project Management
- Project Kickoff Meeting
- Pavement Data Received
271010
Draft Pond Site Report
5- Drainage/Permitting
- Project Kickoff Meeting
- Review Draft Pond Site Report
- Drainage Kickoff Meeting
- Pond Notification Letter - Initial
- Environmental Permit Coordination Meeting
- Drainage Manual & Drainage Design Guide
146005
Title Search Work
9 - Project Management
- Line and Grade/Parcel Feasibility Meeting
- 60% R/W Map Review
170250
PNC Database
7- Survey, Mapping, & Coordination
- PNC Coordinates
- 30% R/W Control Survey Map
294020
Typical Section Submitted
3 - Plans Development/Project Management
- Typical Section Developed
- Typical Section Approved
925010
Pond Notification Letter - Initial
5- Drainage/Permitting
- Draft Pond Site Report
- Pond Notification Letter - Second
- Review Draft Pond Site Report
- Letter Template
587010
VVH Coordination
2- Utilities
- Advance Utility Notification
- Initial Plans Review (Phase II)
109110
Drainage Kickoff Meeting
5- Drainage/Permitting
- Draft Pond Site Report
- Review Draft Pond Site Report
260010
Typical Section Approved
Once the Typical Section is approved construction costs
changes associated with the Typical Section should be
identified and sent to the FDOT PM, updated in LRE, and
quantities reflected in the Phase II plans.
3- Plans Development/Project Management
- Typical Section Submitted
- Line & Grade (Phase I)
- Structure Review of BDR
- Interactive Project Update Meeting (for Minor Projects)
- Environmental Permit Coordination Meeting
- FDM
106310
Survey Alignment Review
7- Survey, Mapping, & Coordination
- Survey Alignment
- 30% R/W Control Survey Map
- FDOT D5 - Survey & Mapping - Map Preparation & Review - QA/QC Management Plan
170150
30% R/W Control Survey Map
7- Survey, Mapping, & Coordination
- PNC Database
- Survey Alignment Review
- 30% R/W Control Survey Map Review
- Right of Way Mapping Handbook
257010
Design Traffic Received
3- Plans Development/Project Management
- Order Design Traffic
- Pavement Design
145040
Environmental Permit Coordination Meeting
5 - Drainage/Permitting
- Draft Pond Site Report
- Typical Section Approved
- Environmental Permit Application Process
- Environmental Permit Agency Review
- All Environmental Permits Clear
-
Permit Coordination Meeting Agenda
- ERP Review checklist
- FDOT D5 Permit Determination Policy Memo
- ACOE Regional Permit SAJ-92
- FDOT D5 SJRWMD Signature Authority Memo
- Memo Gopher Tortoise Permitting in D5
- FDOT D5 SWFWMD Signature Authority Memo
- FDOT D5 SJRWMD SWPPP Policy Memo
- Memo Wetland Boundary & Delineation Policy
- ERP Presentation
271110
Review Draft Pond Site Report
5- Drainage/Permitting
- Drainage Kickoff Meeting
- Draft Pond Site Report
- Pond Notification Letter - Initial
- Pond Notification Letter - Second
- Final Pond Site Report
272030
Update Permits
5- Drainage/Permitting
- Update Permit Status
- Environmental Permit Coordination Meeting
- Updated Permits Clear
313010
Pavement Data Received
3- Plans Development/Project Management
- Coring
- Pavement Design
- Constructability and MOT Review Meeting
925020
Pond Notification Letter - Second
5- Drainage/Permitting
- Pond Notification Letter - Initial
- Review Draft Pond Site Report
- Pond Notification Letter - Final
- Final Pond Site Report
- Letter Template
271020
Final Pond Site Report
5- Drainage/Permitting
- Pond Notification Letter - Second
- Review Draft Pond Site Report
- Pond Notification Letter - Final
- Review Final Pond Site Report
- Drainage Manual & Drainage Design Guide
315020
30% R/W Control Survey Map Review
7- Survey, Mapping, & Coordination
- 30% R/W Control Survey Map
- 60% R/W Control Survey Map
- FDOT D5 - Survey & Mapping - Map Preparation & Review - QA/QC Management Plan
315120
60% R/W Control Survey Map
7- Survey, Mapping, & Coordination
- 30% R/W Control Survey Map Review
- 60% R/W Control Survey Map Review
- Survey & Mapping Office
106110
Mainline Design Survey Database Submittal
7- Survey, Mapping, & Coordination
- Design Survey
- PNC Coordinates
- Line & Grade (Phase I)
- Survey & Mapping Office
925030
Pond Notification Letter - Final
5- Drainage/Permitting
- Pond Notification Letter - Second
- Final Pond Site Report
- Line and Grade/Parcel Feasibility Meeting
- Review Final Pond Site Report
- Letter Template
113010
Line & Grade (Phase I)
3- Plans Development/Project Management
- Mainline Design Survey Database Submittal
- R/W Estimate - Scope
- 30% R/W Control Survey Map Review
- Stakeholders Meeting
- VE Study
- Line and Grade/Parcel Feasibility Meeting
- Review Access Management Report
- Pavement Design
- Typical Section Approved
- Design and Control Vehicle Form
265010
Preliminary Utility Meeting (Major)
2- Utilities
- Mainline Design Survey Database Submittal
- Utility Contact (minor and plans update)
- D5 Utilities Design Office
(connection to FDOT network/VPN is needed)
- UWHC Process Flow-Instructions
114010
Bridge Hydraulics Recommendation
4- Structures/Related Geotech
- Mainline Design Survey Database Submittal
- BDR
- Pre-BDR Meeting
- Structure Review of BDR
- Geotech Foundations Report for BDR
- Florida Bridge Scour Manual
- Drainage Manual & Drainage Design Guide
271120
Review Final Pond Site Report
5- Drainage/Permitting
- Final Pond Site Report
- Pond Notification Letter - Final
Signed Sealed Pond Site Report
133010
Pre-BDR Meeting
4- Structures/Related Geotech
- Bridge Hydraulics Recommendation
- BDR
- Soils and Foundations Handbook
221010
Review Access Management Report
3- Plans Development/Project Management
- Line & Grade (Phase I)
- Line and Grade/Parcel Feasibility Meeting
- FDOT Systems Planning Office
133020
Geotech Foundations Report for BDR
3 - Plans Development/Project Management
- Bridge Hydraulics Recommendation
- Structure Review of BDR
367020
Approved Exceptions/Variations and Submittal of Utility Design Alternatives
3- Plans Development/Project Management
- Exceptions/Variations (Include Utility Design Alternatives)
- Initial Plans Review (Phase II)
- FDM Section 122
- Utility Accommodation Manual
197010
Pavement Design
Note: The Duration of this event will be changed from 40 Days to 30 Days
3- Plans Development/Project Management
- Design Traffic Received
- Pavement Data Received
- Line & Grade (Phase I)
- Pavement Design Review
- Constructability and MOT Review Meeting
- Incorporate Pavement Review Comments
- Pavement Design Publications
197015
Incorporate Pavement Review Comments
3- Plans Development/Project Management
- Design Traffic Received
- Pavement Data Received
- Line & Grade (Phase I)
- Constructability and MOT Review Meeting
- Pavement Design Review
- Pavement Design Approved
115010
BDR
4- Structures/Related Geotech
- Bridge Hydraulics Recommendation
- Pre-BDR Meeting
- Structure Review of BDR
- FDM
900060
Interactive Project Update Meeting (for Minor Projects)
8-Stakeholder Coordination/Public Involvement
- Initial Plans (Phase II)
- Typical Section Approved
- Pavement Design
- Design Survey
- Constructability and MOT Review Meeting
- Initial Plans Review (Phase II)
271030
Signed Sealed Pond Site Report
5- Drainage/Permitting
- Review Final Pond Site Report
- Line and Grade/Parcel Feasibility Meeting
- Drainage Manual & Drainage Design Guide
301010
Line and Grade/Parcel Feasibility Meeting
3- Plans Development/Project Management
- Line & Grade (Phase I)
- Pond Notification Letter - Final
- Signed Sealed Pond Site Report
- Typical Section Approved
- Review Access Management Report
- Phase II Soils Report (Initial)
- R/W Estimate / Line & Grade Completion
- Initial Plans (Phase II)
- Drainage Design
-
Agenda - Line and Grade
-
Line and Grade Invitees
339010
VE Study
3- Plans Development/Project Management
- Project Execution/PE Begin
- Initial Plans (Phase II)
- VE Procedure, Process Maps & Reports
372010
Submit Pavement Type Selection Report (Phase I)
3- Plans Development/Project Management
- Initial Plans (Phase II)
- Constructability and MOT Review Meeting
298030
R/W Estimate - Line & Grade Completion
1- Right of Way Acquisition
- Line and Grade/Parcel Feasibility Meeting
- Initial Plans Review (Phase II)
- Project Scope Debriefing Presentation
238010
Phase I Evaluation of Consultant
3- Plans Development/Project Management
- Line and Grade/Parcel Feasibility Meeting
- Phase II Evaluation of Consultant
- Consultant Evaluation (CE) system
(connection to FDOT network/VPN is needed)
131010
Phase II Soils Report (Initial)
3- Plans Development/Project Management
- Line and Grade/Parcel Feasibility Meeting
- Initial Plans Review (Phase II)
- Soils and Foundations Handbook
- FDM 318 SOIL SURVEY
109010
Drainage Design
5- Drainage/Permitting
- Line and Grade/Parcel Feasibility Meeting
- Initial Plans Review (Phase II)
- Drainage Manual & Drainage Design Guide
- D5’s Drainage Guidelines
113020
Initial Plans (Phase II)
3- Plans Development/Project Management
- Design Survey
- VE Study
- Line and Grade/Parcel Feasibility Meeting
- 60% R/W Control Survey Map Review
- Initial Plans Review (Phase II)
- Title Search Work
- Submit Pavement Type Selection Report (Phase I)
- Interactive Project Update Meeting (for Minor Projects)
315030
60% R/W Control Survey Map Review
7- Survey, Mapping, & Coordination
- 60% R/W Control Survey Map
- 90% R/W Control Survey Map
- FDOT D5 - Survey & Mapping - Map Preparation & Review - QA/QC Management Plan
197020
Constructability and MOT Review Meeting
3- Plans Development/Project Management
- Pavement Design
- Submit Pavement Type Selection Report (Phase I)
- Pavement Data Received
- Initial Plans Review (Phase II)
- Interactive Project Update Meeting (for Minor Projects)
-
Constructability & MOT Meeting Agenda
(connection to FDOT network/VPN or FDOT logon credential is needed)
197030
Pavement Design Review
3 - Plans Development/Project Management
- Pavement Design
- Pavement Design Approved
315140
90% R/W Control Survey Map
7- Survey, Mapping, & Coordination
- R/W Survey
- 60% R/W Control Survey Map Review
- 90% R/W Control Survey Map Review
- Survey & Mapping Office
197040
Pavement Design Approved
3 - Plans Development/Project Management
- Pavement Design Review
- Constructability and MOT Review Meeting
- Typical Section Approved
- Interactive Project Update Meeting (for Minor Projects)
- Initial Plans Review (Phase II)
146010
Title Search Work Updates
7- Survey, Mapping, & Coordination
- Initial Plans (Phase II)
- 90% R/W Control Survey Map
- 60% R/W Map Review
- 90% R/W Control Survey Map Review
315040
90% R/W Control Survey Map Review
7- Survey, Mapping, & Coordination
- 90% R/W Control Survey Map
- 30% R/W Map (Includes Topo)
- FDOT D5 - Survey & Mapping - Map Preparation & Review - QA/QC Management Plan
138010
30% R/W Map (includes TOPO)
7- Survey, Mapping, & Coordination
- 90% R/W Control Survey Map Review
- 30% R/W Map Review
- Survey & Mapping Office
262010
Public Hearing
9 - Project Management
- Develop CAP Strategy
Initial Plans (Phase II)
292010
Public Information Meeting
9 - Project Management
- Develop CAP Strategy
Initial Plans (Phase II)
311010
Structure Review of BDR
4- Structures/Related Geotech
- Bridge Hydraulics Recommendation
- BDR
- Geotech Foundations Report for BDR
- Typical Section Approved
- 30% Structure Plans
- 30% Geotech Foundations Report
- Load Rating Report
900045
Plans in Hand Review w Construction & Utilities
9 - Project Management
- Initial Plans (Phase II)
- Initial Plans Review (Phase II)
900040
Initial Design Team Meeting (Phase II)
3- Plans Development/Project Management
- Initial Plans Review (Phase II)
- Final Plans and Model (Phase III)
- Project Scope Debriefing Presentation
-
Initial Design Team Meeting Agenda
183020
Load Rating Report
4- Structures/Related Geotech
- Structure Review of BDR
- 60% Structure Plans
- BDR
- Submit Load Rating Report
- Email Reports here
- FDOT Load Rating Manual
133030
30% Geotech Foundations Report
4- Structures/Related Geotech
- Structure Review of BDR
- Review 30% Structure Plans
115030
30% Structure Plans
4- Structures/Related Geotech
- Structure Review of BDR
- Load Rating Report
- Review 30% Structure Plans
- Structures Manual
106020
Updated Design Survey Database Submittal
7- Survey, Mapping, & Coordination
- Initial Plans Review (Phase II)
- Certified Design Survey Deliverables
- FDOT Surveying & Mapping Handbook
424010
R/W Design Support Field Review
1- Right of Way Acquisition
- R/W Estimate - Line & Grade Completion
- R/W Estimate - Initial Plans Completion
- PH 4B ROW Service Contract Exec.
450010
Obtain/Verify TIP/STIP Approval
9 - Project Management
- Initial Plans (Phase II)
302010
Initial Plans Review (Phase II)
3- Plans Development/Project Management
- Initial Plans (Phase II)
- Interactive Project Update Meeting (for Minor Projects)
- Pavement Design
- Updated Design Survey Database Submittal
- Constructability and MOT Review Meeting
- Drainage Design
- Approved Exceptions/Variations and Submittal of Utility Design Alternatives
- Phase II Soils Report (Initial)
- R/W Estimate / Line & Grade Completion
- LDCA Approved
- Railroad Contact
- Confirm Local Support for Initial Plans
- Initial Design Team Meeting (Phase II)
- Phase II Evaluation of Consultant
- Respond to Comments Initial Plans (Phase II)
- R/W Estimate - Initial Plans Completion
- Updated Design Survey Database Submittal
- Final Plans and Model (Phase III)
- Utility Contact (minor and plans update)
- Utility Contact 2nd
- Submit Pavement Type Selection Report (Phase II)
-
FDOT Quality Concurrence Letter
(connection to FDOT network/VPN or FDOT logon credential is needed)
- Plans Review and Comments Ch 1.1
- ERC Submittal Form
(connection to FDOT network/VPN or FDOT logon credential is needed)
- Plans Checklist (D-5 CPM Tools)
(connection to FDOT network/VPN or FDOT logon credential is needed)
140010
30% R/W Map Review
7- Survey, Mapping, & Coordination
- 30% R/W Map (Includes Topo)
- Pre-Parcel Review Meeting
- 60% R/W Map
- FDOT D5 - Survey & Mapping - Map Preparation & Review - QA/QC Management Plan
900090
Pre-Parcel Review Meeting
7- Survey, Mapping, & Coordination
- 90% R/W Control Survey Map Review
- 30% R/W Map Review
- R/W Impact Revisions
- Pre-Parcel Review Meeting Process
- Pre-Parcel Review Spreadsheet
264010
Utility Contact (minor and plans update)
2- Utilities
- Respond to Comments Initial Plans (Phase II)
- Initial Plans Review (Phase II)
- DUO/CUC Review
- Utilities Certified
- 100% Final Production Plans Coordination
- Utility Accommodation Manual
- UWHC Process Flow-Instructions
264210
Utility Contact 2nd
2- Utilities
- Respond to Comments Initial Plans (Phase II)
- Initial Plans Review (Phase II)
- DUO/CUC Review
- Utilities Certified
- 100% Final Production Plans Coordination
- Utility Accommodation Manual
- UWHC Process Flow-Instructions
373010
Submit Pavement Type Selection Report (Phase II)
3- Plans Development/Project Management
- Initial Plans Review (Phase II)
- Final Plans and Model (Phase III)
302030
Respond to Comments Initial Plans (Phase II)
3- Plans Development/Project Management
- Updated Design Survey Database Submittal
- Initial Plans Review (Phase II)
- Confirm Local Support for Initial Plans
- Final Plans and Model (Phase III)
- Utility Contact (minor and plans update)
- Utility Contact - 2nd
- Phase III Soils Report
- R/W Impact Revisions
- Pre-Parcel Review Meeting
- FDOT Quality Concurrence Letter
(connection to FDOT network/VPN or FDOT logon credential is needed)
238020
Phase II Evaluation of Consultant
3- Plans Development/Project Management
- Initial Plans Review (Phase II)
- Phase III Evaluation of Consultant
138030
R/W Impact Revisions
7- Survey, Mapping, & Coordination
-Respond to Comments Initial Plans (Phase II)
-Pre-Parcel Review Meeting
-Final R/W Requirements & LOC to S&M
302040
Incorporate Initial Plans (Phase II) Review Comments
3- Plans Development/Project Management
Respond to Comments Phase II Plans
- Utility Contact (minor and plans update)
145010
Environmental Permit Application Process
5- Drainage/Permitting
- Initial Plans Review (Phase II)
- Environmental Permit Coordination Meeting
- Environmental Permit Agency Review
267010
Railroad Contact
3- Plans Development / Project Management
- Initial Plans Review (Phase II)
- Railroad Clear Memo
131020
Phase III Soils Report
3- Plans Development/Project Management
- Respond to Comments Initial Plans (Phase II)
- Final Plans Review (Phase III)
359010
Confirm Local Support for Initial Plans
8- Stakeholder Coordination / Public Involvement
- Respond to Comments Initial Plans (Phase II)
- Initial Plans Review (Phase II)
- Final Plans and Model (Phase III)
322020
Final R/W Requirements & LOC to S&M
7- Survey, Mapping, & Coordination
- R/W Impact Revisions
- 60% R/W Map
307010
Review 30% Structure Plans
4- Structures/Related Geotech
- 30% Structure Plans
- 30% Geotech Foundations Report
- 60% Structure Plans
- 60% Geotech Foundations Report
- FDOT Structures Manual
900050
60% Mapping Team Meeting (Parcel by Parcel)
7- Survey, Mapping, & Coordination
- Title Search Work
- R/W Impact Revisions
- Final R/W Requirements & LOC to S&M
- 60% R/W Map Review
- 90% R/W Map
- 60% Mapping Team Meeting Process
(connection to FDOT network/VPN is needed)
-
ROW Requirement Change Tracking Form
329010
Request Environmental Review
3- Plans Development/Project Management
Start with activity:
-
Initial Plans Review (Phase II)
- Environmental/Certification Complete
139010
60% R/W Map
7- Survey, Mapping, & Coordination
- 30% R/W Map Review
- Final R/W Requirements & LOC to S&M
- 60% Mapping Team Meeting (Parcel by Parcel)
- 60% R/W Map Review
- FDOT Surveying & Mapping Office
264450
Utility Contact (major projects - UWS)
2- Utilities
- Preliminary Utility Meeting
- Initial Plans Review (Phase II)
- DUO/CUC Review
- Utility Accommodation Manual
264050
Utility Contact (for major projects)
2- Utilities
- Review Updated Plans
- DUO/CUC Review
- Utilities Certified
- Utility Accommodation Manual
359030
Confirm Local Support for Updated Plans
8- Stakeholder Coordination / Public Involvement
- Review Updated Plans
- 100% Plans Coordination
222020
Updated Permits Clear
3- Plans Development/Project Management
- Update Permits
- Utilities Certified
- 100% Plans Coordination
- Plans Completed
113030
Final Plans and Model (Phase III)
3- Plans Development/Project Management
- Respond to Comments Initial Plans (Phase II)
- R/W Impact Revisions
- Confirm Local Support for Initial Plans
- Phase II Evaluation of Consultant
- Initial Design Team Meeting (Phase II)
- Initial Plans Review (Phase II)
- Submit Pavement Type Selection Report (Phase II)
- DUO/CUC Review
- Final Plans Review (Phase III)
- Review 90% Structure Plans
- Submittal Checklist
329020
Environmental/Certification Complete
3- Plans Development / Project Management
- All Environmental Permits Clear
- Complete Package to DCPME
298060
R/W Estimate - Initial Plans Completion
1- Right of Way Acquisition
- Initial Plans Review (Phase II)
- 60% Mapping Team Meeting
- Final Plans Review (Phase III)
133040
60% Geotech Foundations Report
4- Structures/Related Geotech
- 30% Structure Plans
- 60% Structure Plans
115040
60% Substructure Plans/60% Structures Plans
4- Structures/Related Geotech
- 30% Structure Plans
- 60% R/W Map Review
- FDM (Section 260)
272010
Environmental Permit Agency Review
5- Drainage/Permitting
- Environmental Permit Application Process
- Environmental Permit Coordination Meeting
- Initial Plans Review (Phase II)
- All Environmental Permits Clear
308010
Review 60% Substructure Plans/60% Strucrures Plans
4- Structures/Related Geotech
- 60% Structure Plans
- 60% Geotech Foundations Report
- 90% Structure Plans
- 90% Geotech Foundations Report
279010
Railroad Clear Memo
3- Plans Development/Project Management
- Railroad Contact
- Complete Package to DCPME
359052
3rd Annual Local Agency Update
8- Stakeholder Coordination / Public Involvement
- 2nd Annual Local Agency Update
212010
Transmit PS&E Package (Central Office)
3- Plans Development/Project Management
- PS&E Review(s)
- Local Agency Letting Update
- Letting Date
370010
Transmit PS&E Package (District)
3- Plans Development/Project Management
- PS&E Review(s)
- Local Agency Letting Update
- Letting Date
359060
Local Agency Letting Update
8- Stakeholder Coordination / Public Involvement
- Transmit PS&E Package (Central Office)
- Transmit PS&E Package (District)
- Letting Date
280010
Letting Date
3- Plans Development/Project Management
- Local Agency Letting Update
- FDOT - Contracts Administration
236010
Final Evaluation of Consultant
3- Plans Development/Project Management
- Letting Date
- Consultant Grades
- Draft Major Consultant Template
- Draft Minor Consultant Template
- Consultant Evaluation Management Template
- Consultant Evaluation Quality Template
971020
Pass the Torch Meeting
1- Right of Way Acquisition
- Letting Date
140020
60% R/W Map Review
The limits of construction are reviewed to ensure that
sufficient right of way has been identified or if excessive,
it is questioned. The title search (or current deed) is
reviewed and parent tract property boundaries are verified.
A field review is held with Appraisal personnel and the consultant
(or in house) project surveyor to verify topographic improvements
and identify any new improvements or to identify any improvements
missed during the initial survey that need to be added to the map.
FDOT Surveying & Mapping sends one set of the 60% R/W Map to
affected Utility Companies.
7- Survey, Mapping, & Coordination
- 60% R/W Map
- 90% R/W Map
- FDOT D5 - Survey & Mapping - Map Preparation & Review - QA/QC Management Plan
133050
90% Geotech Foundations Report
4- Structures/Related Geotech
- 60% R/W Map Review
- 90% Structure Plans
115050
90% Structure Plans
4- Structures/Related Geotech
- 60% R/W Map Review
- Review 90% Structure Plans
- Submit Load Rating Report
315050
R/W Control Survey Map Complete
7- Survey, Mapping, & Coordination
- 60% R/W Map Review
- 90% R/W Map Review
146110
Title Search Update
7- Survey, Mapping, & Coordination
- 60% R/W Map Review
- 100% R/W Map
139020
90% R/W Map
7- Survey, Mapping, & Coordination
- 60% R/W Map Review
- 90% R/W Map Review
325010
Prepare TIITF Package
7- Survey, Mapping, & Coordination
- TIITF Determination
- 60% R/W Map Review
- Documents to R/W
971010
Assemble R/W Team
1- Right of Way Acquisition
- 90% R/W Map Review
- Appraisal Contract
140030
90% R/W Map Review
7- Survey, Mapping, & Coordination
- R/W Control Survey Map Complete
- 90% R/W Map
- 100% R/W Map
- FDOT D5 - Survey & Mapping - Map Preparation & Review - QA/QC Management Plan
303010
Final Plans Review (Phase III)
3- Plans Development/Project Management
- Final Plans and Model (Phase III)
- Phase III Soils Report
- R/W Estimate - Initial Plans Completion
- 100% R/W Map
- R/W Estimate - Final Plans Completion
- FDOT Quality Concurrence Letter
(connection to FDOT network/VPN or FDOT logon credential is needed)
- Phase Review Checklist (CPAM)
184010
Submit Load Rating Report
4- Structures/Related Geotech
- 90% Structure Plans
- Review 90% Structure Plans
- Load Rating Report
- Email reports to: D5-LoadRating@dot.state.fl.us
- FDOT Load Rating Manual
308020
Review 90% Structure Plans
4- Structures/Related Geotech
- Final Plans and Model (Phase III)
- 90% Structure Plans
- 90% Geotech Foundations Report
- Submit Load Rating Report
- DUO/CUC Review
- 100% Structure Plans
139030
100% R/W Map
If required, a cursory review of minor comments from the
90% RW Map Review. If the 90% R/W Map and legal description
review comments are minor and there are no title changes,
this review stage may be waived, and proceed to Final Deliverable.
7- Survey, Mapping, & Coordination
- 90% R/W Map Review
- Title Search Update
- 100% R/W Map Review
- FDOT Surveying & Mapping Office
303030
Respond to Comments Final Plans and Model (Phase III)
3- Plans Development/Project Management
- Final Plans Review (Phase III)
- 100% Final Production Plans Coordination
Confirm Local Support for Final Plans / Update CAP
238030
Phase III Evaluation of Consultant
3- Plans Development/Project Management
- Initial Plans Review (Phase II)
238040
Plans Update Evaluation of Consultant
3- Plans Development/Project Management
- Review Updated Plans
- Consultant Grades
- Draft Major Consultant Template
- Draft Minor Consultant Template
- Grade Approval Instructions
- Sample Consultant Grades Email to Expert
- Sample of Grades Approved by PM
140040
100% R/W Map Review
7- Survey, Mapping, & Coordination
- 100% R/W Map
- R/W Map Complete
- FDOT D5 - Survey & Mapping - Map Preparation & Review - QA/QC Management Plan
264040
DUO/CUC Review
2- Utilities
- Utility Contact (minor and plans update)
- Utility Contact 2nd
- Utility Contact (major projects - UWS)
- Final Plans and Model (Phase III)
- Review 90% Structure Plans
- 100% Final Production Plans Coordination
- 100% Structure Plans
115060
100% Structure Plans
4- Structures/Related Geotech
- Review 90% Structure Plans
- Signed Sealed Geotech Foundations Report
359020
Confirm Local Support for Final Plans
8- Stakeholder Coordination / Public Involvement
- Respond to Comments Final Plans and Model (Phase III)
- 100% Final Production Plans Coordination
310010
100% Final Production Plans Coordination
3- Plans Development/Project Management
- DUO/CUC Review
- Utility Contact (minor and plans update)
- Utility Contact 2nd
- Utility Contact (major projects - UWS)
- Respond to Comments Final Plans and Model (Phase III)
- Confirm Local Support for Final Plans
- Signed Sealed Soils Report
- Plans Completed
- Initial Annual Local Agency Update
266010
Utilities Certified
2- Utilities
- DUO/CUC Review
- Set Contract Time
157010
R/W Map Complete
7- Survey, Mapping, & Coordination
- 100% R/W Map Review
- Instrument Prep
Compatibility Letter Sample
144010
Instrument Prep
7- Survey, Mapping, & Coordination
- R/W Map Complete
- Documents to R/W
- D5 Survey and Mapping
133060
Signed Sealed Geotech Foundations Report
4- Structures/Related Geotech
- 100% Structure Plans
- Plans Completed
310050
100% Plans Coordination
3- Plans Development/Project Management
- Updated Permits Clear
- DUO/CUC Review
- Confirm Local Support for Updated Plans
- Review Updated Plans
- Utilities Certified
- Plans Completed
- Utilities Certified
268010
Documents to R/W
7- Survey, Mapping, & Coordination
- Instrument Prep
349010
PH 4B ROW Service Contract Exec
9 - Project Management
- Documents to R/W
- Appraisal Contract
208010
Appraisal Contract
1- Right of Way Acquisition
- Documents to R/W
- Assemble R/W Team
- Appraisals
- Negotiation
- Appraisal Review
131030
Signed Sealed Soils Report
3- Plans Development/Project Management
- 100% Final Production Plans Coordination
- Plans Completed
201010
Plans Completed
3- Plans Development/Project Management
- Signed Sealed Geotech Foundations Report
- 100% Final Production Plans Coordination
- Set Contract Time
- All Environmental Permits Clear
- R/W Estimate - Final Plans Completion
106040
Certified Design Survey Deliverables
7- Survey, Mapping, & Coordination
- Plans Completed
Sample Letter
- FDOT Surveying & Mapping Handbook
298090
R/W Estimate - Final Plans Completion
1- Right of Way Acquisition
- R/W Map Complete
- Plans Completed
- Documents to R/W
222010
All Environmental Permits Clear
5- Drainage/Permitting
- Plans Completed
- Environmental Permit Coordination Meeting
- Set Contract Time
- Environmental/Certification Complete
120010
Appraisals
1- Right of Way Acquisition
- Appraisal Contract
- Appraisal Review
143010
Appraisal Review
1- Right of Way Acquisition
- Appraisal Contract
- Appraisals
- Negotiation
- Complete Suit Data
129010
Relocation Work
1 - Right of Way Acquisition
- Appraisal Contract
- Appraisal Review
- R/W Demo & Clear Work
121010
Negotiation
1- Right of Way Acquisition
- Appraisal Review
- Appraisal Contract
- Complete Suit Data
- Final R/W Order of Taking
359050
Initial Annual Local Agency Update
8- Stakeholder Coordination / Public Involvement
- Plans Completed
- 100% Final Production Plans Coordination
- 2nd Annual Local Agency Update
- Initial Annual Local Agency Update Meeting Agenda
240010
Complete Suit Data
1- Right of Way Acquisition
- Appraisal Review
- Negotiation
- Final R/W Order of Taking
273010
Final R/W Order of Taking
1- Right of Way Acquisition
- Negotiation
- Complete Suit Data
- R/W Demo & Clear Work
125010
R/W Demo & Clear Work
1- Right of Way Acquisition
- Final R/W Order of Taking
- R/W Certified
359051
2nd Annual Local Agency Update
8- Stakeholder Coordination / Public Involvement
- Initial Annual Local Agency Update
- 3rd Annual Local Agency Update
255010
R/W Certified
1- Right of Way Acquisition
- R/W Demo & Clear Work
- Complete Package to DCPME
933010
Complete Package to DCPME
3- Plans Development/Project Management
- Set Contract Time
- Production Date
- Pre-Spec Meeting
- Production to Letting Guidelines
- Production Transmittal Forms
171010
Set Contract Time
3- Plans Development/Project Management
- Final Plans and Model (Phase III)
- All Environmental Permits Clear
- Utilities Certified
- Complete Package to DCPME
- Pre-Spec Meeting
- Contract Time Template
- Contract Time Presentation
310020
Pre-Spec Meeting
NOTE: Invite DOT Utility Contact if phase 56 (UWHC) plans
are part of the project. The Consultant is to provide plans,
responses to the comments, and any TSP’s.
3- Plans Development/Project Management
- Set Contract Time
- Complete Package to DCPME
- Production Date
- Pre-Spec Meeting Preperation
- Pre-Spec Meeting Agenda
204010
Production Date
3- Plans Development/Project Management
- Complete Package to DCPME
- Certified Design Survey Deliverables
- PS&E Submittal(s)
- PS&E Submittal Checklist
- General Production Package Info
226010
PS&E Submittal(s)
3- Plans Development/Project Management
- Production Date
- PS&E Review(s)
242010
PS&E Review(s)
3- Plans Development/Project Management
- PS&E Submittal(s)
- Transmit PS&E Package (Central Office)
- Transmit PS&E Package (District)
359025
Local Agency Contact Prior to Plans Update
8- Stakeholder Coordination / Public Involvement
- Project Kickoff Meeting
- Negotiate Staff Hours
- S/A for Plans Update
- Order Design Traffic
220010
Plans Update Design Team Meeting
6- Project Initiation / Negotiations
- S/A for Plans Update
- Plans Update
164020
S/A for Plans Update
6- Project Initiation / Negotiations
- Local Agency Contact Prior to Plans Update
- Encumber Phase 32 funds for S/A (Plans Update)
- Plans Update Design Team Meeting
220420
Plans Update
3- Plans Development/Project Management
- Encumber Phase 32 funds for S/A (Plans Update)
- Plans Update Design Team Meeting
- Update R/W Demo & Clear
- Update Permit Status
- Railroad Contact
- Environmental Permit Coordination Meeting
- FDM Chapter 112
220030
Review Updated Plans
3- Plans Development/Project Management
- Plans Update,
- Confirm Local Support for Updated Plans
- Utility Contact (for major projects)
- 100% Plans Coordination
139060
Update Survey
7-Survey, Mapping & Coordination
- Plans Update
139070
Update R/W Map
7-Survey, Mapping & Coordination
- Plans Update
125030
Update R/W Demo & Clear
1- Right of Way Acquisition
- Plans Update
272040
Update Permit Status
5- Drainage/Permitting
- Updated Permits Clear
- Update Permits
900080
TSMO Coordination Meeting
10 - Traffic Operations Coord
- Incorporate Initial Plans and Model (Phase II) Review
- Plans and Model Update
- Final Plans and Model Review (Phase III)
-
TSMO Meeting Agenda