EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Phase: Design
Length: 3.17 miles
City:
County:
Road:
Design Cost: $814,000
Letting: 10/06/2026
Estimated Costs
Construction Cost: $9 Million
About

The purpose of this project is to maintain the segment of State Road (S.R.) 434 (Alafaya Trail) from south of McCulloch Road in Orange County to north of Clonts Street in Oviedo, Seminole County. The project will also upgrade pedestrian curb ramps in some locations in accordance with Americans with Disabilities Act (ADA) standards.

Contact Information
Design Project Manager
Aleacia Spann
(386) 943-5234
Aleacia.Spann@dot.state.fl.us
Design Firm
Ennov8