EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Phase: Design
Length: 0.284 miles
City:
County:
Road:
Design Cost: $399,000
Letting: 12/01/2026
Estimated Costs
Construction Cost: $751,000
About

The purpose of this project is to repave a segment of U.S. 27/U.S. 301/U.S. 441 from SW 10th Street (State Road 200) to NW 4th Street in Ocala to maintain the roadway surface. The project will also upgrade pedestrian curb ramps as needed to comply with current Americans with Disabilities Act (ADA) standards.

Contact Information
Design Project Manager
Ty Garner
(386) 943-5299
Ty.Garner@dot.state.fl.us