450782-1 US 1 from south of SR 400 to north of Fairview Avenue
Project Details
Work Type: | Resurfacing |
---|---|
Phase: | Design |
Length: | 2.92 miles |
City: | |
County: | |
Road: | |
Letting: | 04/29/2026 |
Estimated Costs
Construction Cost: | $9.2 million |
---|
About
This project proposes to resurface U.S. 1 (South Ridgewood Avenue) from Beville Road (State Road 400) to north of Fairview Avenue in Daytona Beach. The FDOT also proposes additional safety improvements along the corridor, including:
- Adding four new midblock pedestrian crossings equipped with Pedestrian Hybrid Beacons (PHBs). The crossings are proposed near Osceola Avenue, south of Shady Place, between South Street and Cedar Street and north of Live Oak Avenue.
- Restriping the roadway to provide buffered bicycle lanes.
- Modifying the median opening at U.S. 1 and Shady Place to reduce the frequency and severity of crashes.
- Adding two raised intersections at Magnolia Avenue and Orange Avenue.
Learn more about PHBs by watching a short video at https://youtu.be/RNQJs6S1MQk?si=dMR_f81lhYci0F2J.
Get Involved
The Florida Department of Transportation (FDOT) held a project open house on Wednesday, February 12. Please see the open house materials in the files below.
Contact Information
Design Project Manager |
---|
Lori Trebitz
(386) 943-5538