450626-1 SR 406 from I-95 to Forrell Ave
Project Details
Work Type: | Resurfacing |
---|---|
Phase: | Design |
Length: | 2.02 miles |
City: | |
County: | |
Road: | |
Design Cost: | $720,000 |
Letting: | 07/07/2027 |
Estimated Costs
Construction Cost: | $5.1 Million |
---|
About
This is a maintenance resurfacing project on State Road 406 (Garden Street) from west of the Interstate 95 (I-95) interchange to Forrell Avenue, excluding the I-95 ramps. A separate project will be making improvements the I-95 and S.R. 406 interchange as part of a resurfacing project on I-95 from S.R. 50 to S.R. 46. That project is FPID No. 450771-1.
Please note the construction start has changed. Work is now expected to begin in spring 2028.
Contact Information
Design Firm |
---|
Connect Engineering, LLC
|
Design Project Manager |
Kevin Powell
(386) 943-5425
Kevin.Powell@dot.state.fl.us
|