450577-1 Orange Ave (SR 527) from Magnolia Ave to SR 50
Project Details
Estimated Costs
Construction Cost: | $529,000 |
---|
About
This is a maintenance resurfacing project Orange Avenue (State Road (S.R.) 527) from Magnolia Avenue to Colonial Drive (S.R. 50) in Orlando. There is an exception from Marks Street to south of Park Lake Street where the road was recently resurfaced. The project will also upgrade pedestrian curb ramps as needed to comply with current Americans with Disabilities Act (ADA) standards.
Get Involved
The Florida Department of Transportation (FDOT) held a public meeting about the project on Thursday, June 6. Please see the meeting information in the files below.
Contact Information
Design Project Manager |
---|
Samuel Jumber
(386) 943-5244
Samuel.Jumber@dot.state.fl.us
|
Design Firm |
Johnson, Mirmiran & Thompson
|