Project Details
Work Type: Bridge Work
Phase: Completed
Length: 0.067 miles
County:
Road:
Construction Cost: $265,000
Project Start: Summer 2024
Est. Completion: Late 2024
About

The purpose of this project is to install solar-powered navigation and clearance lights. Additionally, the project will involve relocating the existing clearance gauge to the outer side of the bridge, facing south, to ensure proper placement.

 