Project Details
Work Type: Signage
Phase: Completed
Length: 38.28 miles
County:
Road:
Construction Cost: $2.49 million
Project Start: Fall 2023
Est. Completion: Summer 2024
About

This project will install one Dynamic Message Sign (DMS) at each of two locations on Interstate 75 (I-75) between milepost 0 and milepost 38 in Marion County.

Contact Information
Communications Team
Joe Callahan
(352) 326-7744 / (352) 620-3020
Joe.Callahan@dot.state.fl.us
Contractor
Traffic Control Devices, Inc.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us