Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.443 miles
City:
County:
Road:
Construction Cost: $5.7 Million
Project Start: Late 2024
Est. Completion: Fall 2025
About

The Florida Department of Transportation (FDOT) is installing operational and safety improvements along State Road (S.R.) 416 (Silver Star Road) from S.R. 438 (Princeton Street) to U.S. 441 (Orange Blossom Trail). In addition to repaving the roadway, the project will install a raised traffic separator east of the S.R. 423 (John Young Parkway) intersection. Concrete traffic islands will also be built at Hansrob Road and the Wawa driveway to limit left turns onto Silver Star Road from these locations. Traffic and pedestrian signal upgrades are planned at key intersections, including Princeton Street, Eunice Avenue, and Mercy Drive. The project will improve safety and accessibility by filling sideway gaps for pedestrians, enhancing connectivity along the paved shoulders for bicyclists, installing bus stops, and reconstructing curb ramps to meet current Americans with Disabilities Act (ADA) standards. Lighting improvements at signalized crosswalks, new signage, and pavement markings are also included.

Contact Information
Communications Team
Annabelle Bruzos Vega
(321) 319-8130
Annabelle.BruzosVega@dot.state.fl.us
Lane Closures
  • Monday, March 10 through Friday, March 14 from 8:30 a.m. to 4 p.m.: Motorists can expect eastbound and right turn lane closures on S.R. 416 from FCEN Florida Central Railroad to John Young Pkwy for road widening work. FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!

  • Monday, Feb. 17 through Friday, Feb. 21 from 8:30 a.m. to 4 p.m.: Motorists can expect eastbound outside single lane and right turn lane closures on S.R. 416 from Princeton St to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, Feb. 24 through Friday, Feb. 28 from 8:30 a.m. to 4 p.m.: Motorists can expect eastbound outside single lane and right turn lane closures on S.R. 416 from Princeton St to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 3 through Friday, March 7 from 8:30 a.m. to 4 p.m.: Motorists can expect eastbound outside single lane and right turn lane closures on S.R. 416 from Princeton St to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 10 through Friday, March 14 from 8:30 a.m. to 4 p.m.: Motorists can expect eastbound outside single lane and right turn lane closures on S.R. 416 from Princeton St to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, Feb. 17 through Friday, Feb. 21 from 8:30 a.m. to 4 p.m.: Motorists can expect an outside eastbound single lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, Feb. 24 through Friday, Feb. 28 from 8:30 a.m. to 4 p.m.: Motorists can expect an outside eastbound single lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 3 through Friday, March 7 from 8:30 a.m. to 4 p.m.: Motorists can expect an outside eastbound single lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 10 through Friday, March 14 from 8:30 a.m. to 4 p.m.: Motorists can expect an outside eastbound single lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Wednesday, Feb. 19 through Friday, Feb. 21  from 7:30 a.m. to 4 p.m.: Motorists can expect an eastbound single lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway for widening, drainage and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, Feb. 24 through Friday, Feb. 28 from 7:30 a.m. to 4 p.m.: Motorists can expect an eastbound single lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway for widening, drainage and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 3 through Friday, March 7 from 7:30 a.m. to 4 p.m.: Motorists can expect an eastbound single lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway for widening, drainage and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 10 through Friday, March 14 from 7:30 a.m. to 4 p.m.: Motorists can expect an eastbound single lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway for widening, drainage and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Sunday, March 9 through Thursday, March 13 from 7 p.m. to 7 a.m.: Motorists can expect eastbound and westbound nightly lane closures on S.R. 416 from John Young Parkway to U.S. 441 for milling and repaving work. FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!

  • Sunday, March 16 through Thursday, March 20 from 7 p.m. to 7 a.m.: Motorists can expect eastbound and westbound nightly lane closures on S.R. 416 from John Young Parkway to U.S. 441 for milling and repaving work. FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!

  • Sunday, Feb. 23 through Thursday, Feb. 27 from 7 p.m. to 7 a.m.: Motorists can expect eastbound and westbound nightly lane closures on S.R. 416 from John Young Parkway to U.S. 441 for milling and repaving work. FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!

  • Sunday, March 2 through Thursday, March 6 from 7 p.m. to 7 a.m.: Motorists can expect eastbound and westbound nightly lane closures on S.R. 416 from John Young Parkway to U.S. 441 for milling and repaving work. FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!

  • Monday, Feb. 3 through Friday, Feb. 21 from 8:30 a.m. to 4 p.m.: Motorists can expect an outside eastbound lane shift into the multidirectional turn lane on S.R. 416 from Mercy Dr. to John Young Parkway.

Project Files