Work Type: Resurfacing
Phase: Design
Length: 1.397 miles
City:
County:
Road:
Design Cost: $1.1 Million
Letting: 09/04/2024
Estimated Costs
Construction Cost: $3.6 Million
About

The purpose of this project is to repave the southbound travel lanes of U.S. 1 (State Road 5) from the FEC Railroad bridge to Grace Street in Titusville. The project will also include traffic signal upgrades at Garden Street (State Road (S.R.) 406), Main Street, Julia Street, South Street (S.R. 405) and Grace Street. Pedestrian safety enhancements include improved crosswalks, pedestrian curb ramp reconstruction to meet current Americans with Disabilities Act (ADA) standards, and construction of sidewalk to connect to existing bus stops.

Contact Information
Design Project Manager
Tyler Burgett
(386) 943-5388
Tyler.Burgett@dot.state.fl.us
Design Firm
Moffatt & Nichol, Inc.