Project Details
Work Type: Resurfacing
Phase: Construction
Length: 2.315 miles
City:
County:
Road:
Construction Cost: $6.6 Million
Project Start: Spring 2025
Est. Completion: Fall 2025
About

This project proposes to repave a section of U.S. 27 (State Road 25) from County Road (C.R.) 33 to Middlesex Road to extend the life of the existing roadway. Operational and safety enhancements include adding a southbound right turn lane to C.R. 25A (south) near the Lake County EMS Support facility and improving the connection at C.R. 25A to the north across from Saxon Boulevard by removing the obsolete section of the Y intersection on the west side of the road. Drainage improvements and construction of a short segment of sidewalk from Lakeside Apartments to the existing sidewalk north of CR 25A (north).

Contact Information
Communications Team
Joe Callahan
(352) 326-7744 / (352) 620-3020
Joe.Callahan@dot.state.fl.us
Lane Closures
  • Sunday, March 23, through Saturday, March 29, nightly from 7 p.m. to 6 a.m.:  Motorists should be advised that there will be overnight rotating northbound and southbound lane closures (only one lane at a time) on U.S. 27 for construction of curbs, sidewalks, and driveway entrances, and possible milling and resurfacing.

    FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy!

    *Lane closures are subject to change due to unforeseen events and weather.