EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.084 miles
County:
Road:
Construction Cost: $7.7 Million
Project Start: Spring 2025
Est. Completion: Late 2025
About

The Florida Department of Transportation (FDOT) is making operational and safety improvements along North Orange Blossom Trail (U.S. 441) from Wadsworth Road to the Lake County line between Apopka and Mount Dora. This project includes resurfacing the roadway to extend its service life and several other significant changes to increase pedestrian and motorist safety.

A key component of the project is reconfiguring the intersection at North Orange Blossom Trail and County Road (C.R.) 500A (Old Highway 441). The current skewed alignment will be corrected by realigning C.R. 500A into a conventional T-intersection. This adjustment will help slow down northbound left-turning vehicles, improve sight distance, and eliminate right-of-way confusion between left-turning lanes. This design will also support future growth in the area.

This project also includes bicycle and pedestrian safety enhancements. Specifically, bicycle keyholes will be added at right turn lanes along the corridor, providing a safer transition for cyclists. For pedestrians, the project will introduce high-visibility crosswalk markings, enhanced lighting, pedestrian refuges, and new pedestrian signals at Stoneybrook Hills Parkway. Additionally, new sidewalk connections will link LakeXpress bus stops on North Orange Blossom Trail to the shared-use path on Stoneybrook Hills Parkway, improving accessibility for public transit users.

Contact Information
Communications Team
Ryan Yglesias
(407) 278-2713
Ryan.Yglesias@dot.state.fl.us
Contractor
Masci General Contractor, Inc.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • Monday, April 21 to Friday, April 25, from 6 p.m. to 6 a.m. the following morning: Motorists can expect alternating single lane closures on the inside and outside lanes of North Orange Blossom Trail (U.S. 441) in both directions, between Wadsworth Road and Sacred Oak Drive. These closures are necessary to allow road crews to install barrier wall and shift traffic ahead of construction activities. 

    FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!

Project Files