Project Details
Work Type: Safety Project
Phase: Construction
Length: 2.522 miles
City:
County:
Road:
Construction Cost: $16.8 Million
Project Start: Spring 2024
Est. Completion: Summer 2025
About

This Florida Department of Transportation (FDOT) project is intended to enhance safety and operations along the corridor of (State Road) S.R. 50 (Colonial Drive) between Pine Hills Road and Tampa Avenue. The project will improve crosswalk conditions and install new signal improvements.

Additionally, the project will modify several existing median openings along the corridor to improve safety and operations.

 

Contact Information
Communications Team
Annabelle Bruzos Vega
(321) 319-8130
Annabelle.BruzosVega@dot.state.fl.us
Lane Closures
  • Monday, Nov 25 to Tuesday, Nov. 26 from 9 a.m. to 6 p.m.: Motorists can expect eastbound, intermittent outside and inside single-lane closures from Pine Hills Avenue to Tampa Avenue for curb and concrete work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy!

  • Monday, Nov 25 to Tuesday, Nov. 26 from 6 a.m. to 4 p.m.: Motorists can expect westbound, intermittent outside and inside single-lane closures from Pine Hills Avenue to Tampa Avenue for curb and concrete workFDOT encourages all roadway users to drive, walk, and ride with caution and courtesy!

  • Monday, Nov 18 to Friday, Nov. 22 from 9 a.m. to 6 p.m.: Motorists can expect eastbound, intermittent outside and inside single-lane closures from Pine Hills Avenue to Tampa Avenue for curb and concrete work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy!

  • Monday, Nov 18 to Friday, Nov. 22 from  6 a.m. to 4 p.m.: Motorists can expect westbound, intermittent outside and inside single-lane closures from Pine Hills Avenue to Tampa Avenue for curb and concrete work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy!

  • Tuesday, Nov. 19 to Friday, Nov. 22 from 9 p.m. to 6 a.m.: Motorists can expect northbound and southbound outside lane road closure for Fairvilla Road north of S.R. 50 for utility and waterline installation. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy and follow all posted detour signs!