Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.185 miles
City:
County:
Road:
Construction Cost: $5.5 Million
Project Start: Early 2025
Est. Completion: Late 2025
About

The Florida Department of Transportation (FDOT) is improving safety and operations on North Orange Avenue (State Road (S.R.) 527) from Magnolia Avenue to north of Rollins Street in Orlando. This project will reconfigure the roadway from Magnolia Avenue to north of Ivanhoe Boulevard to provide one travel lane in each direction and additional on-street parking. In some areas, the curb will be extended to shorten crossing distances for pedestrians, and in other areas, floating islands will be built to help define the on-street parking.

Raised intersections will be constructed at Highland Avenue and Ivanhoe Boulevard to encourage safer driving speeds along the corridor. Additional improvements include milling and resurfacing the roadway, drainage modifications, upgraded pedestrian signalization, and curb ramps to comply with current Americans with Disabilities Act (ADA) standards.

To learn more about Rectangular Rapid Flashing Beacons (RRFBs), including how to use them:

Get Involved

 The Florida Department of Transportation (FDOT) cordially invites you to a casual, informational event we will be hosting regarding our current State Road 527 (North Orange Avenue) construction project (Project No.: 445220-1).

The event will be held at Gaston Edwards Park on Thursday, March 6, from 9 a.m. to 11 a.m., weather and conditions permitting.  

Thank you for your cooperation and for partnering with FDOT in our mission to deliver safe, dependable infrastructure across Central Florida and beyond.

Contact Information
Communications Team
Annabelle Bruzos Vega
(321) 319-8130
Annabelle.BruzosVega@dot.state.fl.us
Contractor
Ranger Construction Industries, Inc.
Lane Closures
  • There are no lane closures at this time.
Project Files
Project Images
(Flyer includes a picture of a steaming coffee cup and a hard hat with coffee beans with text that reads:) Coffee with the Contractor S.R. 527 from Magnolia Ave to north of Rollins St. Stop by for a casual, informative
discussion about the S.R. 527 construction project! Meet the team, ask questions, and get the latest updates over coffee. We look forward to seeing you! Gaston Edwards Park
1236 N. Orange Ave. Orlando, FL 32804 Thursday, March 6 9 a.m. to 11 a.m
Phase 1 Pedestrian Detour Map
RRFB - Pedestrians, see this? Do This!
RRFB - Drivers, see this? Do This!