Project Details
Work Type: Resurfacing
Phase: Construction
Length: 8.404 miles
County:
Road:
Construction Cost: $11 Million
Project Start: Fall 2023
Est. Completion: Late 2024
About

This project will make improvements to State Road (S.R.) 326 from Northwest 12th Avenue to S.R. 40 near Marion County. The project will extend the life of the existing roadway through milling and resurfacing all primary and secondary travel lanes.

Construction improvements include replacing mailboxes, installing asphalt aprons at various locations, paving side street connections, and reconstructing driveways. The project will also replace signage as needed and add new pavement markings. An eastbound to northbound left turn lane will be added at Northeast 49th Street.

At Northeast 40th Avenue Road, an eastbound to southbound right turn lane and a westbound to southbound left turn lane will be added. A new signal will be installed at the Northeast 25th Avenue and Northeast 36th Avenue intersections. New signal heads will allow for protected left turns at the Northeast 58th Avenue intersection.

Contact Information
Communications Team
Matt Young
(352) 326-7744 / (352) 620-3020
MattA.Young@dot.state.fl.us
Contractor
C. W. Roberts Contracting, Inc.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • Sunday, June 23, through Saturday, June 29

    7 a.m. to 4 p.m.: Motorists should expect a daytime right turn lane closure along S.R. 326 eastbound at Northeast 25th Avenue for roadway widening.

    8 p.m. to 7:30 p.m.: Motorists should expect alternating eastbound and westbound single-lane closures along S.R. 326 from Northeast 40th Avenue to S.R. 40 for paving operations. Flaggers will be present. Please slowly approach the construction zone, heed the direction of all signs and flaggers, and cautiously bypass the work zone when safe.