Project Details
Phase: Construction
Length: 4.778 miles
Construction Cost: $219.3 million
Project Start: Early 2023
Est. Completion: Summer 2027
About

This project will provide landscaping to the I-4 and Sand Lake Road interchange project 444315-1. 