EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Phase: Construction
Length: 4.778 miles
Construction Cost: $219.3 million
Project Start: Early 2023
Est. Completion: Summer 2027
About

This project will provide landscaping to the I-4 and Sand Lake Road interchange project 444315-1. 

Lane Closures
  • There are no lane closures at this time.