Work Type: Resurfacing
Phase: Design
Length: 2.616 miles
Design Cost: $740,000
Letting: 01/27/2027
Estimated Costs
Construction Cost: $3.9 Million
About

The purpose of this project is to replace sections of concrete pavement as needed along westbound lanes of East International Speedway Boulevard (U.S. 92/State Road 600) from North Alabama Avenue to east of Kepler Road (County Road 4101) near DeLand. The project will also make intersection upgrades on U.S. 92 at Kepler Road under a goes-with project. (FPID No.: 451257-1).

Contact Information
Design Project Manager
Kevin Powell
(386) 943-5425
Kevin.Powell@dot.state.fl.us
Goes With