EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

This project has been completed and is only available for historical reference.
Project Details
Work Type: Widening
Phase: Completed
Length: 0.867 miles
County:
Road:
Construction Cost: $4.7 Million
Project Start: Summer 2021
Est. Completion: Spring 2022
About

The purpose of this project is to add a center turn lane on State Road (S.R.) 60 from west of S.R. 15/U.S. 441 to east of S.R. 91/Florida's Turnpike. The addition of the center turn lane is to reduce congestion along the S.R. 60 corridor and improve the traffic operations at the Florida's Turnpike on and off ramps and U.S. 441 intersection.

Contact Information
Communications Team
Annabelle Bruzos Vega
(321) 319-8130
Annabelle.BruzosVega@dot.state.fl.us
Contractor
OHLA USA, Inc.
Goes With
Project Files