EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Phase: Design
Length: 0.127 miles
City:
County:
Road:
Design Cost: $1 Million
Letting: 07/29/2026
Estimated Costs
Construction Cost: $3 Million
About

The intent of this project is to alleviate localized flooding at the intersection and adjacent properties along State Road (S.R.) 50 (East Colonial Drive) at Maguire Boulevard in Orlando. The project will increase drainage capacity by adding two pipes on Lakewood Drive and Maguire Boulevard and adding inlets to collect the stormwater. Minor improvements during reconstruction of the roadway are also included.

S.R. 50 within the project limits is a six-lane divided highway. Maguire Boulevard is a City of Orlando facility with two through lanes in each direction at the intersection, plus dedicated turn lanes. Lakewood Drive is a City of Orlando facility with one lane in each direction. Open trench excavation will be required to replace the pipes.

Contact Information
Design Firm
Connelly and Wicker, Inc.
Design Project Manager
Gregory Prytyka
(386) 943-5394
Gregory.Prytyka@dot.state.fl.us
Goes With
Project Files