EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Resurfacing
Phase: Construction
Length: 12.198 miles
City:
County:
Road:
Construction Cost: $14.6 Million
Project Start: Early 2024
Est. Completion: Fall 2024
About

The Florida Department of Transportation (FDOT) will rehabilitate approximately 12 miles of State Road (S.R.) 19 from S.R. 50 to West Oleander Avenue in Lake County, a stretch that connects Groveland to Howey-in-the-Hills. These improvements will enhance safety and operations for drivers, pedestrians, and bicyclists.

In addition to milling and resurfacing the existing roadway, this project will widen S.R. 19 at County Road (C.R.) 478 (Cherry Lake Road) to create a new southbound left turn lane, make drainage adjustments throughout the project, and widen existing shoulders at the U.S. 27 (S.R. 25) off-ramp. Bicycle lanes will be provided as paved shoulders and five-foot unmarked keyholes will be added to right-turn lanes.

Sidewalk curb ramps will be reconstructed to comply with the Americans with Disabilities Act (ADA) standards. Bridge safety improvements will be made at the U.S. 27 and Florida's Turnpike overpasses.

As part of an adjacent project (448876-1), sidewalk improvements are planned from South Florida Avenue to East Lakeview Avenue in Howey-in-the-Hills.

Contact Information
Communications Team
Matt Young
(352) 326-7744 / (352) 620-3020
MattA.Young@dot.state.fl.us
Contractor
C. W. Roberts Contracting, Inc.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • Sunday, June 30, through Saturday, July 6

    7 a.m. to 4 p.m.: Motorists should expect northbound and southbound intermittent single-lane closures along S.R. 19 within the project limits for shoulder treatment and paving operations.

    7 p.m. to 7 a.m.: Motorists should expect a southbound single-lane closure at the U.S. 27 overpass for the installation of temporary barrier wall and crash wall.

    Please slowly approach the construction zone, heed the direction of all signs and flaggers, and cautiously bypass the work zone when safe.

  • Sunday, June 23, through Saturday, June 29, from 7 a.m. to 4 p.m.: Motorists should expect northbound and southbound intermittent single-lane closures along S.R. 19 within the project limits for shoulder treatment and at the U.S. 27 overpass for traffic shift preparation. Please slowly approach the construction zone, heed the direction of all signs and flaggers, and cautiously bypass the work zone when safe.

Goes With