EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Widening
Phase: Design
Length: 2.009 miles
County:
Road:
Design Cost: $4 Million
Estimated Costs
ROW Cost: $5.9 Million
Construction Cost: $37 Million
About

The purpose of this project is to improve operations and safety along State Road (S.R.) 40 (Granada Boulevard) from Breakaway Trail to Williamson Boulevard in Ormond Beach. During design, the recommendations presented in the 2014 Project Development and Environment (PD&E) Study will be further evaluated during design. The concept calls for widening S.R. 40 from 4 to 6 lanes.

Right of way acquisition will be needed for this project and is tentatively scheduled to begin in fall 2025.

Contact Information
Design Firm
Inwood Consulting Engineers, Inc.
Design Project Manager
Marcus Lisicki
(386) 943-5542
Marcus.Lisicki@dot.state.fl.us
Project Files