Project Details
Work Type: Resurfacing
Phase: Construction
Length: 13.993 miles
City:
County:
Road:
Construction Cost: $28.4 Million
Project Start: Early 2023
Est. Completion: Spring 2025
About

The purpose of this project is to resurface Interstate 75 ( I-75) from the Sumter County line to State Road (S.R.) 200. In addition, the existing median crossovers will be reconstructed, the guardrail will be updated and added where necessary. Minor drainage work will also take place.

Contact Information
Communications Team
Joe Callahan
(352) 326-7744 / (352) 620-3020
Joe.Callahan@dot.state.fl.us
Contractor
Anderson Columbia Co.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • 8 p.m. Tuesday, Sept. 3, through 6 a.m. Wednesday, Sept. 5: Motorists should expect an overnight closure of the State Road (S.R.) 200 on-ramp to Interstate 75.

    Detour information: Travelers needing the quickest access to I-75, should head east on S.R. 200 and turn north on Southwest 27th Avenue. Then turn west on S.R. 40 and travel one mile to the southbound I-75 on-ramp.