Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.82 miles
City:
County:
Road:
Construction Cost: $2.9 Million
Project Start: Early 2025
Est. Completion: Spring 2025
About

This project plans to resurface State Road (S.R.) A1A from South 8th Street to North 18th Street in Flagler Beach to extend the life of the existing roadway. Pedestrian improvements are planned, including upgrading intersection crosswalks with pedestrian activated signals known as Pedestrian Hybrid Beacons (PHBs). 

The Pedestrian Hybrid Beacons (PHBs) are located at the following locations:

    • South 8th Street
    • South 3rd Street
    • North 5th Street
    • Moody Boulevard (S.R. 100)

    Reconstruction of pedestrian curb ramps to comply with current Americans with Disabilities Act (ADA) standards is also included.

    To learn more about Pedestrian Hybrid Beacons (PHB), including how to use them:

    Pedestrian Hybrid Beacon Video 

    How to Use a PHB

    Contact Information
    Communications Team
    Debbie Cople
    (386) 740-3566
    Debbie.Cople@dot.state.fl.us
    Lane Closures
    • There are no lane closures at this time.