This project has been completed and is only available for historical reference.
Project Details
Work Type: Widening
Phase: Completed
Length: 2.7 miles
County:
Road:
Project Start: Fall 2022
Est. Completion: Early 2024
About

The purpose of this project was to add one auxiliary lane on both eastbound and westbound I-4 between County Road (C.R.) 532 and State Road (S.R.) 429. The westbound off-ramp to C.R. 532 was widened to two lanes to increase off-ramp flow and capacity. This project mill and resurfaced S.R. 429 between I-4 and Sinclair Road. This project was being constructed in conjunction with FPID No. 443958-1, the combined construction cost is $37,946,386.97. 

For more information, please visit I4Beyond.com/ChampionsGate.