Project Details
Work Type: Resurfacing
Phase: Construction
Length: 13.993 miles
City:
County:
Road:
Construction Cost: $28.4 Million
Project Start: Early 2023
Est. Completion: Fall 2024
About

The purpose of this project is to resurface Interstate 75 ( I-75) from the Sumter County line to State Road (S.R.) 200. In addition, the existing median crossovers will be reconstructed, the guardrail will be updated and added where necessary, and minor drainage work will take place.

Contact Information
Communications Team
Matt Young
(352) 326-7744 / (352) 620-3020
MattA.Young@dot.state.fl.us
Contractor
Anderson Columbia Co.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • Sunday, April 28, through Friday, May 10, from 8 p.m. to 6 a.m. and 6 p.m to 6 a.m. (for guardrail installation): Motorists should expect overnight northbound and southbound lane closures on Interstate 75 (I-75) from C.R. 484 to S.R. 200 and from the Sumter County line to C.R. 484 for milling and paving and median grade improvements. Shoulder closures will be in effect at the Sumter County line for attenuator replacements.

    At the 66th Street crossing on I-75, expect inside northbound and southbound shoulder closures from 6 p.m. to 6 a.m. within the same date range for guardrail installation.

    For safety, please reduce your speed, alertly merge into an open lane and cautiously bypass the construction zone.