Project Details
Work Type: Interchange Construction
Phase: Completed
Length: .535 miles
County:
Road:
Construction Cost: $17 Million
Project Start: Fall 2017
Est. Completion: Summer 2019
About

The scope of this project includes the construction of a new interchange at I-95 and the existing Viera Boulevard overpass. This new interchange is expected to improve mobility in the area by relieving traffic congestion at the two adjacent I-95 interchanges, Fiske Boulevard to the north and Wickham Road to the south. These improvements will  help to accommodate future projected traffic demand and improve driver safety and efficiency.

Diverging Diamond Interchange (DDI) Video

Contact Information
Contractor
Jr. Davis Construction Company, Inc.
Communications Team
Ashley Ingham
(321) 634-6111
Ashley.Ingham@dot.state.fl.us
Project Files