About this Project:
-
Widen and reconstruct existing 5-lane rural roadway to 6-lane urban divided roadway with raised 30’ median, sidewalks, and irrigation sleeves from W. of CR 545 (Avalon Blvd.) to SR 429 (Western Beltway) (MP 3.019 – 6.075)
-
Closed drainage system to include four ponds within FDOT Right-of-Way
-
Signalization to include new mast arms, pedestrian signals, and interconnect at 8 intersections
-
Signing and pavement marking to current FDOT standards
-
Utility coordination and relocation is anticipated, including a Utility Work by Highway Contractor with the City of Winter Garden for the construction and relocation of sanitary sewer and water facilities
-
Potential Landscaping and Hardscaping elements to be coordinated with City of Winter Garden
|
Project Details:
• Contract #: E5N44
• County: Orange
• Total Cost: $16,857,750.00
• Est. Completion: Summer 2011
• Contractor: Prince Contracting, LLC / C3TS
• Project Website: Not Available
Contact Person:
• Steve Olson, (407) 482-7813, (386) 943-5479
Send Comments and Questions: Here
|
|
Lane Closures:
September 5, 2010 - September 11, 2010
- No lane closures anticipated by the Contractor
August 29, 2010 - September 4, 2010
- 08/30/10 - 8/31/10, Monday - Tuesday
- 9 pm - 6 am
- Intermittent lane closures on SR 50 and Dillard Street
- 08/29/10- 09/3/10
- 9 pm - 6 am
- Intermittent lane closures on SR 50 between CR 535 and SR 429 by the City of Winter Garden
|